COMMERCE BUSINESS DAILY ISSUE OF JULY 24,1995 PSA#1394U. S. Army Corps of Engineers, Omaha District, 215 North 17th Street,
Omaha, NE 68102-4978 Y -- CONSOLIDATED BASE SUPPORT COMPLEX - PHASE I & II, ELLSWORTH AFB
SOUTH DAKOTA SOL DACA45-95-B-0100 DUE 091295 POC Contact Contracting
Division at: (402)221-4266. The work will include the following:
(Approx. quantities) New Work Includes: A two story administrative
office building comprised of approximately 68,300 GSF. The complex will
have various offices, conference rooms, and computer rooms.
Construction materials include CMU bearing walls with 4'' face brick,
cast stone trim, slab on grade first floor, precast concrete second
floor, steel frame roof, standing seam metal roofing, aluminum windows,
gypsum board interior partitions, wood interior doors and frames,
acoustical tile ceilings, VAV HVAC system, sprinkler fire protection,
plumbing, and fluorescent lighting. Site Work Includes: eleven (11)
acres of clearing and grubbing, 8,000 CY of cut, 11,000 CY of fill, 800
LF of sanitary sewer, 1,500 LF of storm sewer, 200 LF of water main,
150 LF of gas main, 750 LF of 1,500 KVA electrical feed, 1,500 KVA
transformer, 2,000 A/480V switchboard, 10,700 SY of bituminous
pavement, seeding, sod, and landscape planting. Demolition Work (remote
sites) Includes: six (6) existing two story wood frame buildings
comprising 83,000 GSF. The estimated construction cost of this project
is between $10,000,000 and $15,000,000. Contractor's Quality Control
will be a requirement in this contract. The Contractor will be required
to commence work within 10 days after notice to proceed and complete
the work 540 calendar days after receipt of Notice to Proceed.
Provisions will be included for liquidated damages in case of failure
to complete the work in the time allowed. Performance and payment bonds
will be required. Bid sets will be available on/a August 10, 1995.
Half-size plans and specifications will be furnished upon request. All
requests for solicitation packages should be made in writing no later
than 14 days prior to bid opening. After such time, packages will be
furnished if supply is available. It has been determined that the
number of sets be limited to 1 (one) per firm (additional copies will
be the responsibility of the requestor). Please list street address
(for parcel del service) and mailing address. SPECIAL NOTES: All
responders are advised that this requirement may be cancelled or
revised at any time during the solicitation, selection, selection
evaluation, negotiation and/or final award structure and disposition of
US Armed Forces. Small & Disadvantaged Businesses are encouraged to
participate & will be used to maximum extent practicable as both prime
& subcontractor. (0201) Loren Data Corp. http://www.ld.com (SYN# 0141 19950721\Y-0007.SOL)
Y - Construction of Structures and Facilities Index Page
|
|