COMMERCE BUSINESS DAILY ISSUE OF AUGUST 4,1995 PSA#1403U.S. Army Corps of Engineers, Fort Worth District, P.O. Box 17300, 819
Taylor Street, ATTN: CESWF-CT, Fort Worth, TX 76102-0300 Z -- REPAIR OIL/WATER SEPARATOR AND STORM DRAIN LINE IN MOTOR POOL,
USARC, WACO, TEXAS SOL DACA63-95-B-0161 DUE 091895 POC Jan Cook,
Contract Specialist, (817/334-3476). Project is for the demolition of
an existing in-ground concrete wash rack, the installation of a new
in-ground concrete wash rack, and the installation of a government
furnished water wash recycling system. Work includes a pre-fabricated
metal building to house the wash rack and all related site work
including grading, entrance gates, and associated mechanical and
electrical equipment and connections. Estimated Cost Range: $25,000 to
$100,000 - - Drawings are bound in the specification at a cost of
$15.00. Requests by mail must include payment in the applicable amount
by company check or money order made payable to F&A Officer USAED FTW
and sent to: USACE, Attn: Room 13A42, Post Office Box 17300, 819
Taylor Street, Fort Worth, Texas 76102-0300. NO EXPRESS MAIL PROCEDURES
WILL BE UTILIZED ON INITIAL MAILINGS OF PLANS AND SPECIFICATIONS.
Requests in person may be paid by cash. No refund will be made and
materials need not be returned. If project is cancelled or no award is
made, cost of plans and specifications will be refunded only on
written request. Solicitation to be issued on or about 18 Aug 95. Bid
opening on or about 18 Sep 95. Duration of contract 115 days. THIS Is
A 100 PERCENT SMALL DISADVANTAGED BUSINESS SET-ASIDE. OFFERS FROM
CONCERNS OTHER THAN SMALL DISADVANTAGED BUSINESS CONCERNS Are NOT
SOLICITED. SIC Code for this procurement is 1541, Small Business Size
Standard is $17 million. (0214) Loren Data Corp. http://www.ld.com (SYN# 0182 19950803\Z-0014.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|