COMMERCE BUSINESS DAILY ISSUE OF AUGUST 16,1995 PSA#1411EG&G Mound Applied Technologies, P.O. Box 3000, OSW-4, Miamisburg, OH
45343-3000 Y -- SM, WD, T-WEST & SW BUILDING STACKS EFFLUENT SAMPLING UPGRADES
Sol 208355-5853 Due 102695 Contact Chris Draut, 513/865-3147 EG&G Mound
Applied Technologies operates the Mound plant for the U.S. Department
of Energy under prime contract number DE-AC24-88DP43495. The purpose of
this project is to install isokinetic sampling equipment and
radionuclide monitors on five exhaust air stacks. Some of the sampling
and monitoring equipment will be Government Furnished Equipment (GFE).
Construction will include the demolition of some nuclear ductwork;
installation of new nuclear ductwork; two sampling/monitoring
instrument sheds; A/C system for instrument sheds and one existing
room; S.S. sample tubing down stacks and through buildings; telephone
and electronics wiring; power distribution; construction of safety
ladders and stack maintenance platforms on three of the stacks. Some
construction work will be at 200 foot elevation. Some work will be in
radiological control areas. Note: This is a 100% set-aside for small
business concerns. Percentage of work by prime contractor: 25%. SIC
Code: 1541. Period of performance: 180 calendar days. Estimated cost
range: $750,000 to $1,000,000. Solicitation available 09/21/95. Bid
opening date: 10/26/95, 4:00 p.m. Request in writing from: Architect
Engineering Firm: Barge, Waggoner, Summer & Cannon, Inc. Leslie
Jacobowitz (513-438-0378) (Fax: 513-438-0379 ; 8755 Gander Creek Road,;
Miamisburg, OH 45342. A non-refundable $60.00 deposit will be required,
send the deposit with the written request for the bid package. Make
checks payable to Barge, Waggoner, Sumner & Cannon. (223) Loren Data Corp. http://www.ld.com (SYN# 0206 19950815\Y-0007.SOL)
Y - Construction of Structures and Facilities Index Page
|
|