COMMERCE BUSINESS DAILY ISSUE OF AUGUST 18,1995 PSA#1413NASA Langley Research Center, MS 144, Industry Assistance Office
Hampton, Va. 23681-0001 Z -- CONSTRUCTION/MODIFICATIONS TO COCKPIT TRANSLATION SYSTEM SOL
1-081-GGK1.1187 DUE 100595 POC Bid Distribution Office,(804)864-2547.
The work to be performed includes, but is not limited to, the
following: furnishing and install a 14 ton, double girder, top running
bridge, electric overhead traveling bridge, crane, complete with
rails, electrification, controls, and 14 ton electric wire rope hoist;
construction of a 1500 square foot mezzanine; construction of a
catwalk; furnish and install raised flooring; lighting, communication,
and fire alarm systems; and extension of a sprinkler system under
raised flooring and mezzanine. Contract duration 110 days--Estimated
cost range between $100,000 and $250,000--All responsible sources may
submit a bid which will be considered by the Agency--Bid opening is
approximate--Solicitation available approximately 9/5/95. (0228) Loren Data Corp. http://www.ld.com (SYN# 0170 19950817\Z-0018.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|