COMMERCE BUSINESS DAILY ISSUE OF september 15,1995 PSA#1432Contract Division, Accounting Department, Water, Resources Development
Public Corporation, 5-3-3 Y -- JAPAN: S16 CONSTRUCTION POC Tel 81/3/3584-1251 FAX N/A product
data a industry sector code: B detailed product description:
construction Title: construction of the second todoroki bridge at the
takizawa dam; site: left Bank: aza-nirogi; right Bank: opposite of
nirogi, oaza-otaki, otaki-mura, chichibu-gun, saitama-ken; summary:
superstructure work: five-span continuous, prestressed concrete rigid
frame box-girder bridge; length, 345 meters; span length, 35.0, 75.0,
125.0, 75.0, and 35.0 meters; width, 8.25 to 9.25 meters; piers: four
units; height, 58.5, 16.5, and 13.5 meters; skeleton, pillar and wall
type; foundation: caisson-type piles, six holes (3.5- meter bore, two
holes; 4.0-meter bore, two holes; 10.5-meter bore, two holes; total
length, 140 meters); abutments: two units; skeleton, inverted T-type;
foundation: caisson-type piles, four holes (2.5-meter bore, two holes;
3.0-meter bore, two holes; total length, 82.0 meters); construction
period: 870 days; main materials to be used: concrete, approx. 13,000
cubic meters; reinforcing steel, approx. 2,660 tons; prestressing
steel, approx. 150 tons. C product specifications/technical data: N/a
(not available) D quantity: N/a e U.S. dollar value: N/a F other
information: N/a response data a response language: Japanese. B best
way to respond: letter. C from manufacturers only: N/a D information
desired from U.S. firm: N/a e primary buying factor: the lowest bid
within the estimated price range. F other information: pre-screening is
required to be eligible for bidding. Pre-screening deadline: 16:00 pm,
sep. 21, 1995. Bid documents must be obtained directly from the
procuring agency, not from U.S. Embassy. Payment in yen. A issuing
agency: Water Resources Development Public Corporation B financing
agency: same as above. C price of bid documents: N/a D purchase bid
documents by: 16:00 pm, oct. 20, 1995. E Tender number required in all
communications: N/a F performance bonds required: not required. G
closed procurement procedure: no. H bidding procedures: open
competitive Tender. I bid deadline: 14:00 pm, oct. 31, 1995. J other
information: ''kensetsu kogyo shimbun'': 9/12/95. Eligible Tender
participants must be pre-qualified firms that meet the following
criteria: 1) firms that do not fall under any of the following
categories: a) firms that have not been rehabilitated from insolvency
or bankruptcy; B) firms that have -- in the past year, in a Contract --
deliberately performed a poor work, or unfairly cheated on quality and
quantity of materials; interfered with fair competition, damaged fair
pricing, or colluded for unfair profit; prevented a winner from
signing a Contract, or a contractor from carrying out a Contract;
prevented an official from conducting supervision or inspection;
unjustifiably reneged on a Contract; and employed, as representative,
manager, or equivalent in a Contract, those who perpetrated one of the
above-described Acts within one year of their misconduct; and C) firms
whose business is judged extremely unsound; 2) consortia comprised of
two firms pre-qualified for open competitive or selective bidding on
steel superstructure work by this Corporation; 3) consortium member
firms combined must have completed both (a) and (B) projects, described
below; each member firm must have, as the main contractor, completed
either (a) or (B) and constructed the superstructure of a prestressed
concrete bridge of any size: a) construction of superstructure of a
prestressed concrete bridge of at least 100 meters in span length,
using the cantilever erection method; and B) construction of foundation
using caisson-type piles of at least eight meters in bore. Note: only
construction projects in which bidders have had a 20 percent or greater
share of involvement are eligible for consideration; 4) firms that can
assign, to the construction site, a field representative and a chief
engineer or engineering supervisor who meet the following criteria: a)
have, since 1990, had experience with construction of either (a) or
(B) as described in item (3) above; field representative and chief
engineer or engineering supervisor combined must have completed both
(a) and (B) projects; B) in the case of chief engineer or engineering
supervisor, is qualified as a certified first-class construction
supervisor under the construction business law, or is qualified for
construction, agricultural civil engineering, or forestry civil
engineering under the engineers law; and C) in the case of engineering
supervisor, is qualified to supervise designated construction work; 5)
member firms must not be currently suspended from designation by this
Corporation; and 6) member firms must not be related by capital or
personnel to the cotractors involved in this project. Post remarks Post
contact/prepared by haomori approved by gtaevs akasaka, minato-ku,
Tokyo 107, Japan Please send a copy of your response to: Commercial
Officer (FCS TOP), American Embassy, Tokyo, Unit 45004, APO Ap 96337,
Refer to TC600. Please note: All correspondence with the Awarding
Authority and/or the Procuring Agency MUST be in Japanese.. (0256) Loren Data Corp. http://www.ld.com (SYN# 0054 19950914\Y-0001.SOL)
Y - Construction of Structures and Facilities Index Page
|
|