COMMERCE BUSINESS DAILY ISSUE OF NOVEMBER 9,1995 PSA#1470DA, Tulsa District, Corps of Engineers, POB 61, Tulsa, OK 74121-0061 C -- USADACS ADMINISTRATION COMPLEX, MCALESTER ARMY AMMUNITION PLANT,
MC ALESTER, OKLAHOMA POC Jimmy White, A-E Contracts/Document Section,
(918) 669-7043, or Carl Webster, Military Design Section, (918)
669-7161, 1645 S. 101st East Avenue, Tulsa, OK 74128. 17. 1. CONTRACT
INFORMATION: A firm fixed-price architect- engineer contract will be
negotiated for the concept, preliminary, and final design and
construction phase services (optional) for the subject project. All
work must be performed by or under the direct supervision of licensed
professional engineers and/or architects. The project design will be
developed using the metric (SI) system of measurements. This
procurement is unrestricted. The anticipated contract award date is Jan
96 and the final completion date is Dec 96. All responders are advised
that this requirement may be cancelled or revised at any time during
the solicitation, evaluation, selection, negotiation, or final award
process based on decisions related to DOD changes in force structure
and disposition of US Armed Forces, and are advised that the contract
award date(s) and final completion date(s) may vary. If a large
business is selected for this contract, and the contract amount exceeds
$500,000, it must comply with FAR52.219-9 regarding the requirement for
a subcontracting plan on that part of the work it intends to
subcontract. For your information, the subcontracting goals for Tulsa
District are 65% for small business and 10% for small disadvantaged
business. The plan is not required with this submittal. 2. PROJECT
INFORMATION: Key elements of this project are: project consists of
construction of a) multi-story, brick/veneer 40,000 SQ FT General
Purpose Administration Building to accommodate administrative
personnel, technical library, TV/Video production studio, photo lab,
ADP center, and printing service. b) Open bay metal building 43,200 SQ
FT Transportation Test Facility to accommodate Ammunition Peculiar
Equipment (APE) prototype development and transportability testing with
administrative offices, vibration and noise isolation rooms, and
electronics lab. Facility to have rail access, testing track and
truck-rail dock. c) Two pre-engineered metal buildings, 20,000 SQ FT,
East Warehouse, and 15,000 SQ FT West Warehouse, warehouses to
accommodate inert items such as tacical vehicles, APE materials, APE
prototypes, inert ammunition containers, and concrete block lockable
areas for secure storage. d) Building Information System. Provide
supporting facilities including gas, water, sewer, electrical,
communications, information systems, fire protection systems, intrusion
detection systems, air conditioning, and site work elements, parking,
sidewalks, rail, storm drainage systems, security lighting. The
estimated construction cost is between $ 10M and $ 20M . 3. SELECTION
CRITERIA: See Note 24 for general selection process. The selection
criteria in descending order of importance are: a. Specialized
experience and technical competence in (1) recent design of similar
type military facilities, (2) construction cost estimating and
preparation of estimates on IBM Compatible personal computers using
Corps of Engineers Computer Aided Cost Estimating System (M-CASES Gold)
(software provided), (3) producing CADD drawings in either Intergraph
Micro Station, or Micro Station PC Format, (4) producing quality
designs, (5) ability to access a Computerized Automatic Review
Management System (ARMS) via modem, and (6) construction phase
services. b. Past performance on DoD and other contracts with respect
to cost control, quality of work, and compliance with delivery
schedules. c. Qualified professional personnel with experience in the
following disciplines, but not limited to: architect, civil, corrosion
control, electrical, environmental, fire protection, mechanical, and
structural engineering. Other required team members are landscape
architects, specification writers, and estimators. d. Sufficient
capacity to submit the Concept Design by April 1996, and complete the
design by December 1996. e. Location of the firm in the general
geographical area of the project. f. Volume of DoD contract awards in
the last 12 months as described in Note 24. 4. SUBMITTAL REQUIREMENTS:
See Note 24 for general submittal requirements. Interested firms
having the capabilities to perform this work must submit one copy of SF
255 (and a SF 254 for the prime firm and all consultants) to the above
address no later than 4:30 p.m. on the 30th day after the date of this
announcement. If the 30th day is Saturday, Sunday or Federal Holiday,
the deadline is 4:30 p.m. of the next business day. Solicitation
packages are not provided. This is not a request for proposal. The SF
255 should specifically addres the requirements of this announcement.
Responding firms are requested to clearly identify those tasks to be
performed in-house and at what office, and those tasks to be
subcontracted and at what office. Responding firms are requested to
identify all computer capabilities in Block 10 of the SF 255. Also in
Block 10 of the SF 255 describe the firm's design quality control plan,
including coordination with subcontractors. Cover letters and
extraneous material are not desired and will not be considered.
Personal visits to discuss this contract will not be considered. This
is not an RFP. (0311) Loren Data Corp. http://www.ld.com (SYN# 0012 19951108\C-0001.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|