COMMERCE BUSINESS DAILY ISSUE OF DECEMBER 11,1995 PSA#1487USDA, Forest Service, Lolo National Forest, Attn: Contracting, Building
24, Fort Missoula, Missoula, MT 59801 Y -- SEELEY LAKE WAREHOUSE CONSTRUCTION SOL R1-16-96-183 DUE 012296.
Contact Point, Judy Martin, 406/329-3889, Contracting Officer, Joan A.
McNab, 406/329-3950. The Forest Service required the construction of
an approximately 3,250 Sq. Ft. warehouse on the Seeley Lake Ranger
District, Lolo National Forest, Missoula County, MT. The warehouse
consists of various storage and work areas, meeting and locker area
including restrooms and showers. The work is estimated to start on
April 1, 1996. Bids are due January 22, 1996. Contract time will be 180
calendar days. The estimated price range is between $100,000 and
$250,000. All responsible sources may submit an offer which will be
considered. (339) Loren Data Corp. http://www.ld.com (SYN# 0151 19951208\Y-0013.SOL)