COMMERCE BUSINESS DAILY ISSUE OF DECEMBER 28,1995 PSA#1499Alliant Techsystems Incorporated, Allegany Ballistics Laboratory, P.O.
Box 210, State Route 956, Rocket Center, (Mineral County) WV 26726 Y -- INFORMATION MANAGEMENT CENTER - BLDG. 440 SOL PHC-187 DUE 030896.
Contact Point, Patrick H. Cunningham, 304/726-5047. The work consists
of the construction of a two story building, measuring approximately
9,060 SF per floor for a total of 18,120 SF, and related sitework. The
building consists of concrete foundations, below grade concrete walls
with waterproofing, slab on grade, structural steel framing, bar
joists, elevated concrete slab on metal deck, metal roof deck with
rigid insulation and EPDM single-ply roofing, combination brick and
glass exterior, building and sound control insulation, interior metal
stud with gypsum board and concrete masonry unit partitions, moveable
partitions, suspended ceilings, ceramic and vinyl tile, carpet,
washroom partitions and accessories, elevator, HVAC, restrooms, fire
protection, electrical power and lighting, communications wiring,
security access control systems, and incidental related work. Sitework
consists of earthwork, underground utilities, reinforced earth modular
block retaining walls, cast in place concrete and brick paver
sidewalks, patios, and stairs, landscaping, exterior lighting, and
incidental related work. Estimate range for the total effort is between
$2,000,000 & $5,000,000. Bonds will be required. West Virginia
Contractors License must be submitted prior to commencement of work by
Contractor and all Subcontractors. $35 NON-REFUNDABLE FEE payable to
Alliant Techsystems must be submitted with written request to obtain
plans and specifications. Alliant reserves the right to refuse written
requests for plans and specifications after February 15, 1996. (355) Loren Data Corp. http://www.ld.com (SYN# 0064 19951227\Y-0002.SOL)
Y - Construction of Structures and Facilities Index Page
|
|