COMMERCE BUSINESS DAILY ISSUE OF JANUARY 24,1996 PSA#1516Commanding Officer, Navy Public Works Center, Naval Facilities
Engineering Command Contracts, Code 220, Pearl Harbor, HI 96860-5470 Y -- Y-FIRM FIXED PRICE CONTRACT TO REPLACE AFTERBURNER REFRACTORY AT
BUILDING 1430, PEARL HARBOR NAVAL SHIPYARD, OAHU, HAWAII SOL
N62755-95-Q-8732 DUE 021396 POC Contact Point: A. Ching, (808)474-8043;
Contracting Officer: A. Yuen, (808)474-3385. The work includes
replacing the existing refractory tiles at the bottom cone of the
afterburner, replacing existing throat tiles, welding smoke inlet tubes
to cone plate, adjusting existing ring tubes and incidental related
work for the smoke abatement system at the Firefighting School. The
contractor shall commence work 15 calendar days after award and
complete the entire work 14 calendar days after work has started.
Estimated cost is between $25,000 and $200,000. The closing date for
requesting RFQ package is 6 February 1996. This procurement is
unrestricted. SIC Code 1741 applies. (0022) Loren Data Corp. http://www.ld.com (SYN# 0103 19960123\Y-0010.SOL)