COMMERCE BUSINESS DAILY ISSUE OF JANUARY 26,1996 PSA#1518DA, Tulsa District, Corps of Engineers, POB 61, Tulsa, OK 74121-0061 Z -- ALTER CHEMICAL CLEANING ROOM, BUILDING 1055, TINKER AIR FORCE BA
SE, OKLAHOMA SOL DACA56-96-B-0032 DUE 031296 POC Chief, Contracting
Division, 918/669-7275. Construct a temporary chemical cleaning process
and relocate existing process equipment including installation of
temporary piping, electrical, and exhaust systems. Demolish existing
cleaning area including removal of ceiling and mechanical/electrical
systems as required. Demolition will include removal of asbestos
containing floor tile. Construct a new Class 300,000 chemical cleaning
facility including new metal stud walls, gypsum board ceiling, air
lock vestibule, environmental control system, process exhaust system,
process piping, and electrical power/lighting systems. Also included
will be the construction of a new mechanical room, reinstallment of
existing process equipment, balancing, testing and commissioning of new
mechanical/electrical systems, and the removal of all temporary
facilities. Estimated cost range of this project is from $100,000 to
$250,000. An advanced non-refundable fee of $17.00 (half size) and
$25.00 (full size) is required for each set of specifications. Make
check payable to F&A Officer, USAED, Tulsa, and mail to the attention
of Contracting Division. Payment must be received prior to issuance of
plans and specifications. Plans and specifications will be available
7 Feb 96. No phone calls to order please. All orders will be mailed via
first class mail. Request for special handling (Federal Express,
Overnight Express, etc.) will not be honored. (0024) Loren Data Corp. http://www.ld.com (SYN# 0111 19960125\Z-0006.SOL)