COMMERCE BUSINESS DAILY ISSUE OF MARCH 20,1996 PSA#1555U.S. Property & Fiscal Office, Camp Lincoln, 1301 N MacArthur Blvd,
Springfield, Illinois 62702-2399 C -- A&E CONTRACT TO DESIGN THE COMPOSITE OPERATIONS & TRAINING,
COMPOSITE SQUADRON OPERATIONS, MEDICAL TRAINING FACILITY FOR RELOCATION
OF 126TH AIR REFUELING, O'HARE, IL TO SCOTT AIR FORCE BASE, BELLEVILLE,
IL POC Contact Point, Brian S. Creech, Contract Specialist, (217)
785-3682. The United States Property and Fiscal Office for Illinois
proposes to enter into a firm fixed price Architect/Engineer contract
to provide Type A, B, design and an option for C inspection services
for the design of facilities listed above for the 126th Air Refueling
Wing from Chicago to Scott Air Force Base. The types of facilities and
approximate square footage of the facilities are as follows: Composite
Operations & Training Facility 23,700 sf; Composite Squadron Operations
34,400 sf; Medical Training Facility 4,00 sf. Firms desiring
consideration are invited to submit both SF 254 and SF 255 no later
than 30 days after publication of this announcement to USPFO-IL-P&C,
Attn: Brian S. Creech, 1301 N. MacArthur Blvd., Camp Lincoln,
Springfield, Illinois 62702-2399. When submitting the SF 254 and 255,
include the number and dollar value of Architect/Engineer contracts
awarded by DoD agencies during the previous twelve (12) months. Type A
(Investigative Services) - Accomplish field surveys and investigations
which may include soil investigations, topographic surveys; analysis of
existing facilities and utilities; study of various mechanical,
electrical, and structural systems as a basis for recommended
functional and safety designs; perform environmental assessments as may
be required to make proper site selection and to determine basis of
design, and perform other investigations as necessary to make a
complete design. Prepare a conceptual design submittal, including
preliminary site plans, typical cross sections and narrative
description of proposed structural design, mechanical electrical
systems, and economic or other justification for selected systems.
Prepare a cost estimate of the major elements of the project and
confirm if the project can be accomplished within budget, fact finding
investigations, to provide pertinent design data and information
including coordination with users and reviewing authorities to produce
complete designs Type B (Pre-Final and Final Design) - Prepare
detailed Architectural/Engineering design calculations, site plan, and
utility plan, prepare outline specifications, detailed cost estimate,
furnish final design, detailed working drawings and specifications,
final design analysis, final cost estimates, and obtain any required
construction/environmental permits. Type C (Inspection Services) -
Inspection of construction, review of shop drawings and material
submittals and preparation of asbuilt drawings. Evaluation criteria in
descending order of importance are: (1) Professional Qualifications
necessary for satisfactory completion of required services, to include
experienced program manager, architect, civil engineer, mechanical
engineer, electrical engineer, structural engineer and related support
personnel. (2) Specialized experience and technical competence in the
type of work required. (3) Capacity to accomplish the work in the
required time. (4) Past performance on contracts with government
agencies and private industry in terms of cost control, quality of
work, and compliance with performance schedules. (5) Location in the
general geographical area of Scott Air Force Base and knowledge of the
locality of the project. (6) Volume of work previously awarded to the
firm by the Department of Defense in the past twelve (12) months. The
Government's obligation for award of this contract is contingent upon
the availability of appropriated funds. This procurement is
unrestricted. See Note 24. (075) Loren Data Corp. http://www.ld.com (SYN# 0021 19960319\C-0011.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|