COMMERCE BUSINESS DAILY ISSUE OF APRIL 17,1996 PSA#1575U.S. Army Construction Engineering Research Labs. (USACERL), ATTN:
Contracts Office, P.O. Box 9005, Champaign, IL 61826-9005 44 -- SUPPLY BOILER FOR DEMONSTRATION OF LOW EMISSION CYCLONIC
COMBUSTION SOL DACA88-96-R-0014 DUE 052196 POC Ms. Rita S. Hyer,
Contract Specialist, (217)352-6511, ext. 7280, or Ms. Deloras J.
Adamson, Contracting Officer (217)373-7297. The U.S. Army Construction
Engineering Research Laboratories (USACERL) require one (1)
factory-assembled, package type boiler with burner, steam drum,
controls, and appurtenances (fan not required) mounted to the maximum
practical extent as an integral unit on a steel base. An option is
included to provide an economizer feature to the boiler as well. The
boiler will be used for a demonstration of new technology on low
emission cyclonic combustion which occurs in two stages. In the first,
fuel and air are injected at high velocity into a cylindrical
combustion chamber. The combustion gases are cooled by heat transfer to
the water surrounding the combustion chamber and by steam injection. In
the second stage, more air is introduced to complete combustion. The
modified commercial burner required shall use this cyclonic combustion
for burning natural gas and number 2 fuel oil (not concurrently) in a
100% watertube-walled horizontal combustion chamber. The boiler shall
be capable of continuously providing steam at a maximum flow of
100,000 and a minimum of 12,500 pounds per hour. Boiler efficiency
shall not be less than 82% at 100% maximum continuous rating (MCR)
while firing natural gas and using steam injection. The boiler shall be
delivered to the Central Power Plant at Watervliet Arsenal, New York.
Installation will not be required under this contract. A warranty
against defective design, workmanship, or material for a period of two
(2) years from the date of delivery shall be included. The Government
requires delivery of the equipment within approximately eight months
after award of the contract. Request for Proposal (RFP) No.
DACA88-96-R-0014 will be issued on or about 6 May 96 with the closing
date on or about 21 May 96. Offerors shall have at least two (2)
boilers in successful service for a minimum of two (2) years prior to
the closing date of the solicitation. Award will be made to the lowest
responsible offeror who demonstrates the capability to meet all the
requirements described in the solicitation, including the past
performance requirement described above, and meet the Government's
delivery schedule. Submissions shall be in accordance with the RFP and
all qualified sources may apply. Multiple awards will not be made
under this solicitation. Requests for copies of this solicitation shall
be made in writing and addressed to USACERL, Attn: Contracts Office,
P.O. Box 9005, Champaign, IL 61826-9005, or may be submitted by
facsimile to (217)373-6773. (0106) Loren Data Corp. http://www.ld.com (SYN# 0183 19960416\44-0001.SOL)
44 - Furnace, Steam Plant, Drying Equipment and Nuclear Reactors Index Page
|
|