COMMERCE BUSINESS DAILY ISSUE OF MAY 28,1996 PSA#1603U. S. ARMY CORPS OF ENGINEERS, OMAHA DISTRICT, 215 NORTH 17th STREET
OMAHA, NE 68102-4978 Y -- REHABILITATION OF FEDERAL STREAMBANK STABILIZATION SOL
DACW45-96-B-0060 DUE 071296 POC Contract Specialist: Barb Rennert (402)
221-4114. The project is located along the left and right banks of the
Missouri River, between river miles 800 and 753 in South Dakota and
Nebraska. The project consists of (Approx. quantities) rehabilitating
3065 feet of revetment, 30 feet of hardpoint, and 25 feet of refusal.
This work will require placement of approximately 6385 tons of stone.
The estimated construction cost of this project is between $100,000 and
$250,000. Contractor's Quality Control will be a requirement in this
contract. The Contractor will be required to commence work within 10
days after notice to proceed and complete the work 90 calendar days
after receipt of Notice to Proceed. Provisions will be included for
liquidated damages in case of failure to complete the work in the time
allowed. Performance and payment bonds will be required. All requests
for solicitation packages should be made in writing and no later than
14 days prior to bid opening. After such time, packages will be
furnished if supply is available. It has been determined that the
number of sets be limited to one (1) per firm. Orders shall be by
written request or faxed to (402) 221-4530. Questions regarding the
ordering of same and bidding matters should be made to: 402-221-4266.
Telephone calls regarding small business matters should be made to Mr.
Hubert J. Carter Jr. at 402-221-4110. Telephone calls on contents of
drawings and specifications should be made to Marylee Stobbe at (402)
221-4411. SIC NO. 1799. SOLICITATION IS UNRESTRICTED AND OPEN TO BOTH
LARGE AND SMALL BUSINESS PARTICIPATION. (0144) Loren Data Corp. http://www.ld.com (SYN# 0133 19960524\Y-0008.SOL)
Y - Construction of Structures and Facilities Index Page
|
|