COMMERCE BUSINESS DAILY ISSUE OF JULY 30,1996 PSA#1647Contracting Officer, Coconino National Forest, 2323 E Greenlaw Lane,
Flagstaff AZ 86004-1890 Y -- STREAMBANK STABILIZATION, CAVE SPRINGS CAMPGROUND SOL IFB
R3-04-96-14. Due 083096. Contact Contracting Office Yolanda B Mitchell
at (520) 527-3540. Project will include mobilization, minor water
diversion and dewatering of the work site, and placement of a grouted
rock streambank stabilization structure on approximately 430 feet along
the west bank of Oak Creek. Project is located at the Cave Springs
Campground approximately 13 miles north of Sedona on Highway 89A.
Contract time is estimated at 75 days with a desired start date of
September 16, 1996. Price range is $50,000 to $100,000. (204) Loren Data Corp. http://www.ld.com (SYN# 0215 19960729\Y-0041.SOL)
Y - Construction of Structures and Facilities Index Page
|
|