COMMERCE BUSINESS DAILY ISSUE OF AUGUST 8,1996 PSA#1654USDA, Forest Service, East Zone Contracting, P.O. Box 130, Bozeman, MT
59771 Y -- TAYLOR FORK ROAD BRIDGE REPLACEMENT SOL R1-11-96-34 DUE 092696
POC Elaine Hilliard, Gen'l. Info. (406) 587-6763 Remove existing 2-span
native timber bridge and replace with single span concrete bridge 67
feet long in same location. Major work items include installation of a
gov't furnished temporary bypass bridge, demolition and disposal of
existing bridge, install concrete footings & gov't furnished concrete
beams. Construction of approaches, riprap & guardrails. Contract time
120 calendar days. Gallatin County, Bozeman RD, Gallatin National
Forest, MT. Package will be available on or about 8/26/96. Price Range
between S25,000 and S100,000. Not Set aside for Small Business.
(0219) Loren Data Corp. http://www.ld.com (SYN# 0190 19960807\Y-0016.SOL)
Y - Construction of Structures and Facilities Index Page
|
|