COMMERCE BUSINESS DAILY ISSUE OF JANUARY 9,1997 PSA#1758USAED, Sacramento, Attn: A-E Negotiations Section, 1325 J Street, Room
1079, Sacramento, CA 95814-2922 C -- POTENTIAL FIXED PRICE CONTRACT FOR DESIGN/ADDITIONS OR
ALTERNATIONS OF LIGHT INDUSTRIAL PROJECTS/VEHICLE MAINTENANCE SHOPS IN
SUPPORT OF THE SACRAMENTO DISTRICT PROGRAM SOL DACA05-97-R-0010 DUE
020797 POC Mr. Ken Parkinson, Unit Leader, A-E Negotiations Unit (916)
557-7470. Contracting Officer Judith Grant. (Site Code DACA05). 1.
CONTRACT INFORMATION: Work and services may consist of the design for
various types of light industrial facility/maintenance type facilities
including such projects as warehouse facilities, maintenance shops and
simple processing facilities in support of the Sacramento District's
assigned military design program in various fiscal years. The projects
may generally be in the states of CA, AZ, NV and UT. This may be the
only announcement which may lead to the award of A-E contracts for the
design of light industrial facility/maintenance type facilities
projects for the Sacramento District during the next 12 months. A
separate firm-fixed-price contract will be negotiated and awarded for
each project. A list of at least three firms will be selected. When a
design authorization for the first project of this type is received,
negotiations will begin with the top ranked firm. When an authorization
is received for a subsequent project, or if negotiations with a firm
for a project are unsuccessful, negotiations will begin with the next
ranked firm that has not been offered a project for negotiation. If the
list of ranked firms is exhausted, the negotiation cycle will begin
again with the top ranked firm. If the performance of a firm is less
than average, the firm will not be considered for added work during the
cycle. None of the projects have been authorized for design and funds
are not presently available for any contracts. This announcement is
open to all businesses regardless of size. All interested
Architect-Engineers are reminded that in accordance with the provisions
of PL 95-507, they will be expected to place subcontracts to the
maximum practicable extent consistent with the efficient performance of
the contract with small and small disadvantaged firms. If a large
business is selected, it must comply with FAR 52-219.9 regarding the
requirement for a subcontracting plan on that part of the work it plans
to subcontract. The following subcontracting goals are the minimal
acceptable goals to be included in the subcontracting plan. Of the
subcontracted work, 55% to small business, 8.5% to small disadvantaged
business (subset of small business), and 3.0% to woman-owned small
businesses (subset of small business). The contractor shall be
responsible for design and drawings using computer-aided design and
drafting (CADD) and delivering the three-dimensional drawings in
Autodesk AutoCAD CADD software, release 12, MS-DOS, version 6.2 using
Windows 3.1, electronic digital format. The Government will only accept
the final product for full operation, without conversion or
reformatting, in the Autodesk AutoCAD release 12 format, and on the
target platform specified herein. The target platform is a 486 DX, with
DOS version 6.2 operating system with Windows 3.1. Drawings produced by
scanning drawings of record or containing photographic images shall be
delivered in a raster format compatible with the target platform
AutoCAD electronic digital format. Drawing files shall also be
delivered in Computer-aided Acquisition and Logistic Support (CALS)
electronic digital format; the specifications will be produced either
in SPECS INTACT with Standard Generalized Markup Language (SGML) or
other word processing program compatible with WordPerfect 6.1 using the
Corps of Engineers Military Construction Guide Specifications.
Specification files shall also be delivered in PostScript electronic
digital format; responding firms must show computer and modem
capability for accessing the Criteria Bulletin Board System (CBBS) and
the Automated Review Management System (ARMS). The firms selected for
these contracts will be required to submit a detailed subcontracting
plan at a later date. If the selected firms submit a plan with lesser
goals, it must submit written rationale of why the above goals were not
met. A detailed plan is not required to be submitted with the SF 255;
however, the plans to do so should be specified in Block 10 of the SF
255. This work will include all architectural-engineering (A-E) and
related services necessary to complete the design, and A-E services
during the construction phase for these projects. 2. PROJECT
INFORMATION: These contracts may include the design of hangar bays and
shops, maintenance areas, office and personnel support areas, parts
and/or equipment storage, interior security features and computer
rooms. The facilities may also include fire sprinkler systems, site
improvements, utility connections, electrical, heat, air conditioning,
communication, fencing and paving. If demolition of existing
facilities is required, the design effort with documents developed for
asbestos and/or lead based paint removal may be required. An
interactive design charrette process for data gathering may be
utilized. These projects may be designed using the metric system of
measurement and responding firms shall indicate metric design
experience in block 8. The estimated construction costs per project
range from $1,000,000.00 to approximately $10,000,000.00. 3. SELECTION
CRITERIA: See Note 24 for general selection process. Theselection
criteria are listed below in descending order of importance. Criteria
"a" through "d" are primary. Criteria "e" through "g" are secondary and
will only be used as "tie-breakers" among technically equal firms. a.
Specialized experience and technical competence in (1) Design of new
and alteration of light industrial and maintenance type projects as
described above. b. Past performance on DOD and other contracts with
respect to cost control, quality of work and compliance with
performance schedules. c. Qualified professional personnel in the
following key disciplines: Project Manger, Architecture, Civil,
Electrical, Mechanical, Structural and Geotechnical Engineers,
Communications, Cost Estimating, and Certified Industrial Hygienist.
The evaluation will consider education, training, registration, overall
relevant experience and longevity with the firm. d. Capacity of firm to
accomplish work in the required time frame including professional
qualifications of firm's staff and consultants to be assignedto the
projects pertinent to that required for these projects. The breadth and
size of a firm will be considered to match the complexity/simplicity of
the expected projects. e. Volume of DoD contract awards in the last 12
months as described below. f. Location of the firm in the general
geographical area of the Sacramento District's area of responsibility.
g. Extent of participation of small business, small disadvantaged
business, woman owned small business, historically black colleges and
universities or minority institutions in the proposed contract team,
measured as a percentage of the total estimated effort. 4. SUBMISSION
REQUIREMENTS: See Note 24 for general submission requirements.
Interested Architect-Engineer firms having the capabilities to perform
this work are invited to submit ONE (1) completed SF 255 (11/92
edition) US Government Architect-Engineer and Related Services
Questionnaire for Specific Project for themselves and ONE (1) completed
of SF 254 (11/92 edition) for themselves and one for each of their
subcontractors to the office shown above, ATTN: A-E Negotiations Unit.
In block 7 of the SF 255 provide resumes for all key team members,
whether with the prime firm or a subcontractor; list specific project
experience for key team members; and indicate the team members role on
each listed project (project manager, architect, design engineer,
etc.) In block 9 of the SF 255, responding firms must indicate the
number and amount of fees awarded on DoD (Army, Navy, and Air Force)
contracts during the 12 months prior to this notice, including change
orders and supplemental agreements for the submitting office only. In
block 10 of the SF 255, provide the design quality management plan and
organization chart for the proposed team. A task specific quality
control plan must be prepared and approved by the government as a
condition of contract award, but is not required with this submission.
Responses received by the close of business (4:30 p.m.) on the closing
date will be considered for selection. If the closing date is a
Saturday, Sunday or Federal Holiday, the deadline is the close of
business on the next business day. No other notification will be made
and no further action is required. Solicitation packages are not
provided for A-E contracts. This is not a request for proposals. All
responsible sources may submit the required SF 255 and SF 254 which
shall be considered by the agency. See Numbered Notes 24 and 26.