COMMERCE BUSINESS DAILY ISSUE OF JANUARY 24,1997 PSA#1768AETC CONS/LGCR 550 D Street East Ste 08 Randolph AFB TX 78150-4434 Y -- ADD/ALTER COMMISSARY YUMA AZ SOL F41689-97-B0001 DUE 040797 POC
Melvin McIntosh WEB: aetc business opportunities,
http://www.contractingaetc.af.mil/cgi-bin/afbop. E-MAIL: aetc
contracting squadron, mcintoshm@rndgate1.aetc.af.mil. The project
provides for addition and upgrade to the Commissary facility at Yuma
MCAS AZ. Work includes but is not limited to the following:
Construction of an addition approximately 3,000 SF expanding the front
end of the commissary to allow for new entrance and exit vestibules as
well as new administrative offices, cashier/cash counting office,
bagger's breakroom, patrons' restroom and customer waiting area. In
addition, a 5,600 square foot addition will be constructed to the west
end of the building for the new produce processing and storage rooms,
dairy storage, pre-pkg/poultry storage and expanded receiving aisle.
The sitework will include some concrete and paving as well as utilities
work. Alterations to the store will include demolition of existing
administrative offices, cold storage rooms, exterior canopy, etc., for
making the renovations that will include but limited to new mechanical
mezzanine, new walk in coolers, expansion of the sales area, expansion
of the frozen food sales area, expansion of the checkout area, new
shopping cart storage, new refrigerated display cases along with new
refrigeration compressor racks will be required, new HVAC equipment
will be required, new lighting, fire protection, replacement of
non-refrigerated equipment and complete decor package. Alterations in
the warehouse will include new administration offices. Some asbestos
and lead paint abatement, as well as roof replacement will be required.
Phasing of overall construction work will be required through the
duration of the project to allow for full operation of the commissary.
Proposed procurement is open to both large and small business
concerns. The magnitude of construction is between $1,000,000.00 and
$5,000,000.00. Bid guarantee is required. Bid package should be
available on or about 3 March 1997. Time for project completion is
approximately 14 months. This time is approximate. The actual date will
be established at the time bidding documents are available. Telephone
requests for this solicitation will not behonored. Written requests
should cite IFB No F41689-97-B-0001. Datafax to 210-652-2737, AETC
CONS/LGCR, ATTN: Melvin McIntosh. Requests for solicitation should
include the 9-digit zip code.***** (0021) Loren Data Corp. http://www.ld.com (SYN# 0084 19970124\Y-0003.SOL)