COMMERCE BUSINESS DAILY ISSUE OF JANUARY 31,1997 PSA#1773Defense Supply Service-Washington, Rm 1D245, The Pentagon, Washington,
DC 20310- 5200 A -- BROAD AGENCY ANNOUNCEMENT/EVALUATION OF HIGHLY EFFECTIVE CHEMICAL
SUPPRESSANTS -- PART 1 OF 2 DUE 041197 POC Contact Ms. Sally Williams,
Contract Specialist (703) 693-5017, Contracting Officer, Joyce Rose
(703) 695-2564 BROAD AGENCY ANNOUNCEMENT -- The Executive Director,
Strategic Environmental Research and Development Program (SERDP) is
soliciting proposals to identify and test highlyeffective chemical
suppressants as new and more effective fire suppression technologies.
[NOTE: In addition to this BAA, proposals will be also be solicited
with the government.] BACK-GROUND: Halon 1301, used for fire
extinguishment and explosion suppression applications infielded weapon
systems and mission-critical facilities, has been banned from national
productiondue to its high ozone- depleting potential. Alternatives
developed by industry to date have sizableweight and volume penalties,
and their application to fielded current weapons systems couldrequire
expending large amounts of funding and time. Consequently, the DoD has
embarked onan aggressive new R&D program -- the Next-Generation Fire
Suppression Technology Program(NGP) -- under the technical direction
and oversight of the Office of the Director, DefenseResearch and
Engineering/Advanced Technology (ODDR&E/AT). The NGP goal is to
developand demonstrate, by 2004, retrofitable, economically feasible,
environmentally-friendly and user-safe processes, techniques, and
fluids that meet the operational requirements currently satisfiedby
halon 1301 systems in aircraft, ships, land combat vehicles, and
critical mission supportfacilities. The results will be specifically
applicable to fielded weapons systems, and will providedual-use fire
suppression technologies for preserving both life and operational
assets. Successful candidates must perform satisfactorily in tests for
a wide variety of properties, including those reviewed by the
Environmental Protection Agency (EPA). An initial survey of fires for
which the DoD currently uses halon 1301 shows an extremely broad range
of fire conditions and several distinct hazards to be avoided. The
Military Departments and other participating government agencies will
conduct research projects within the NGP, and proposals accepted from
industry or academia for NGP research projects will be incorporated
into these programs. Additional information on the NGP, including
preliminary information about the types of fires to be suppressed, may
be found on the Internet Web site http://www.dtic.mil/ddre/, under
Science and Technology Programs, at document titled The Next-
Generation Fire Suppression Technology: Strategy for a National
Program, dated July 1996. The NGP Technical Point of Contact is Dr.
Richard G. Gann, Technical Program Manager (TPM), NGP, National
Institute of Standards and Technology (NIST), e-mail (preferred):
rggann@nist.gov, phone: (301) 975-6866; fax: (301) 975-4052. BAA
OBJECTIVE: To identify and evaluate the full range of chemically
activesuppressants that are as, or more, effective than halon 1301
(CF3Br), and sufficiently low intoxicity and environmental impact. To
meet this objective, the principal investigator (PI) mustdevelop a list
of candidates with high flame suppression efficiency and appropriately
low toxicity.The chemicals should be applicable to the types of fires
identified in Appendix A of the NGPStrategy Document. New chemicals
must be synthesized as necessary. The PI should performextinguishment
and flame structure experiments on strained diffusion flames to verify
or adapt firesuppression principles; perform post-flame analyses to
identify potential by-products; and runscreening tests from Elements
3.a and 3.b [Contact the NGP Technical Point of Contact] forsuppression
effectiveness, toxic potency, environmental impact, and residue to
estimateacceptability. PRODUCTS: The outcome of work under this project
will be (a) a list ofpromising chemically-active compounds with
pertinent information on their physical and chemicalproperties,
suppression efficiency, toxicity, storage stability, and breakdown
products (includingtheir properties and toxicities); and (b) full
documentation of the procedures used and the results. Depending on the
success of the NGP in identifying new chemicals and this effort in
evaluatingthem, a successive project within this Element may be
advertised to continue this work. BACKGROUND: Exploratory studies have
shown that several families of compounds (e.g.,organometallics and
phosphonitrilics) are at least as efficient as halon 1301 as flame
inhibitors andhave zero zone depletion potential (ODP). Although some
are too toxic, others are potentiallynon-toxic and may have desirable
chemical and physical properties. SERDP Program Office Resources: The
government estimate of the cost and time to meet the requirements of
this Project is $1.0M over three years, with an estimated first year
cost of $300,000. Proposers should not consider these estimates to be
either minimums or maximums; they are provided only as estimates around
which reasonable proposals may be developed. It should be understood,
also, that the government reserves the right to fund more than one
proposal either to meet this requirement fully or to pursue more than
one innovative approach; the reasonable total cost of which might
bemore or less than the government estimate. The government will
consider proposals which offer technical or cost advantages but only
meet partial technical requirements in this BAA. Estimated additional
funding (cost sharing) from performing organizations:
colleges/universities and small business firms-10% of total request:
all others-33% of total request. SUBMISSIONS: Offerers are encourages
to submit concise, but descriptive, proposals. Proposals for FY 1998
contract awards will be accepted until 4:00 PM EST on April 11, 1997.
The Proposal, including the original signed copy, five additional
copies, and one copy on a 3 1/2" diskette (DOS-formatted, MSWord 6.0 or
lower, or WordPerfect) all referencing BAA ##-## and must be submitted
to: Brenda J. Batch, Administrative Officer, SERDP Program Office, 901
North Stuart Street, Suite 303, Arlington, VA 22203, TEL (703)
696-2123; FAX: (703) 696-2114. All technical questions concerning this
BAA should be addressed to Dr. Richard G. Gann. PROPOSALS SENT BY FAX
OR E-MAIL WILL BE REJECTED. Proposals will be selected through a
technical/scientific/business decision process with technical and
scientific considerations being most important. The primary basis for
selecting proposals shall be technical, importance to the NGP and funds
availability. Individual proposal evaluations will also consider the
acceptability or non-acceptability without regard to other proposals
submitted under the announcement; however, due to budgetary
constraints, all acceptable proposals may not be funded. No award will
be made without a proposal to perform the specific effort within an
estimated cost and time framework. Offerers, if selected, must be
willing to cooperate and exchange information in an integrated program
with other contractors chosen by the TPM. PROPOSAL CONTENT: Proposals
shall be prepared in two sections, Part I and Part II, and able to be
separated for review purposes. Part I shall provide the technical
proposal and management approach, and Part II shall address costs.
Proposalsshall be prepared on 8.5 x 11 inch paper, with one and
one-half line spacing or double spaced, in no less than 11-point size,
any font. All margins (top, bottom, left, and right) shall not be less
than 1". The proposal shall address and be relevant to the listed
evalation criteria listed herein. In addition, Part I of the proposal
shall include: (a) a cover page including BAA number; proposal title;
SERDP Log Number; developed by SERDP; submitting organization, office
code, and address; Contractor DUNS Number and CAGE Code; Principal
Investigator's name, mailing address, telephone number, electronic mail
address, and facsimile machine number; Administrative/Contracting
Representative mailing address, telephone number, electronic mail
address, and facsimile machine number; total estimated cost and
duration; (b) a one-page summary of any technical ideas to be pursued
and their expected impact on the state of the art and the NGP; (c) a
statement of work detailing the scope of the proposed work and specific
utilization of subcontractors; (d) a description of results, products,
and transferable technology expected from the project; (e) a list of
the milestones and schedule; (f) a statement of the technical rationale
that substantiates the schedule and justifies the overall technical
approach of the proposal; (g) a not-to-exceed-one-page summary of any
proprietary claims to results, prototypes, or systems supporting and/or
necessary for the use of the research, results, and/or prototype (if
there are not proprietary claims this section shall consist of a
statement to that effect); (h) a section describing relevant
capabilities, accomplishments, and work in these or closely related
areas along with the qualifications of proposed subcontractors; (i) a
management plan describing the overall approach to management of this
effort, including brief discussions of total organizations, use of
personnel, project/function/subcontractor relationships, government
research and facility interface, and planning, scheduling and control
practices. Part I must be no longer than 15 pages (not including the
cover page, appendices or curriculum vitae). Foldouts shall be counted
as a single page. The contents of the appendices shall be limited to
figures that directly support items discussed in the text of the
proposal. If items are included in the appendices which are not covered
in the basic proposal, the proposal may not be reviewed. Proposals with
Part I in excess of 15 pages may not be reviewed. Proposals of fewer
than the maximum number of pages will not be penalized. PART II of the
proposal is not page limited, but should be very concise and address
the elements listed below and in Appendix A to this BAA. A one-page
summary will be included. Tabs, table of contents,
introduction/executive summary are neither required nor desired. Costs
shall be supported by detailed breakdowns of labor hours by labor
category and tasks/subtasks, materials, travel, computer and other
direct and indirect costs. An explanation of any estimating factors,
including their derivation and application shall be provided. Details
of any cost sharing to be undertaken by the Offerer should also be
included in the cost section. [See APPENDIX A of this BAA for
additional requirements and amplifying information concerning
preparation of Part II cost data.] ABSTRACT: Offerers, either
individual or teamed, are strongly encouraged to submit a two-page
abstract of their proposed work to preclude unwarranted effort (a) on
the part of an Offerer in preparing a full proposal and (b) on the part
of the government, in reviewing one. Page one shall be a title page
clearly labeled PROPOSAL ABSTRACT and including this BAA number,
proposal title, plus Offerers administrative and technical points of
contact along with mailing addresses, telephone and facsimile numbers,
e-mail addresses, and the signature of an authorized officer. The
second page should include a summary of the technical ideas proposed
and their anticipated deliverables, and total cost. The abstract shall
be on 8.5 x 11 inch paper, with one and one-half line spacing or
double spaced, in at least 11-point type, any font. All margins (top,
bottom, left, and right) shall not be less than 1". The original and
one copy of each abstract shall be received no later than February 21,
1997, by: Brenda J. Batch, Administrative Officer, SERDP Program
Office, 901 North Stuart Street, Suite 303, Arlington, Virginia 22203,
TEL: 703-696- 2123; FAX: 703-696-2114. A copy of the abstract should
also be sent -- preferably by e-mail -- to the Technical Pointof
Contact, Dr. Richard G. Gann, by the same date. An abstract is not a
requirement forsubmission or selection of a proposal. Any Offerer whose
abstract is found to be consistent withthe intent of this BAA will be
invited by February 28, 1997, to submit a full technical and
costproposal. Such an invitation does not assure subsequent contract
award. Regardless of therecommendation, the decision to submit or not
submit a proposal is the responsibility of theOfferer. EVALUATION/AWARD
PROCESS: Evaluation of the abstracts and proposals will be performed
using the following criteria, listed in descending order of relative
importance: (1) technical quality and originality of the proposed
research; (2) relevance to the NGP goal and impact on the goal if
successful; and (3) The Offerers capabilities, related experience,
facilities, techniques, or unique combinations thereof, which are
integral factors for achieving the proposed objectives; and (4) the
appropriateness and cost realism of the budget for accomplishing the
work proposed under this BAA. Proposals will be evaluated and ranked by
a Selection/Peer Review Panel chaired by the NGP TPM. The primary basis
for selecting proposals for acceptance shall be technical importance to
the NGP and funds availability. The Panel is composed of members of the
NGP Technical Coordinating Committee, the SERDP Pollution Prevention
Technical Thrust Area Working Group (PP/TTAWG), and/or other selected
reviewers as needed by the Chairman. The Panel and the PP/TTAWGwill
recommend to the SERDP Executive Director, through the Halon
Alternatives R&D Steering Group (HASG), a subset of the acceptable
proposals for award which will construct a balanced program meeting the
NGP needs. These recommended proposals will then be reviewed by the
SERDP Scientific Advisory Board (SAB). The mission of the SAB is to
review all proposed SERDP funded projects and make appropriate
recommendations to the SERDP Council on technical merit and funding.
The TPM will make a concise (30 minute) presentation of the proposals
to the SAB, usually in the Washington, D.C., metropolitan area.
Principal investigators of the recommended projects may attend, as
coordinated with the TPM, who will provide specific guidance for this
presentation, including date, time, and location. Contract award
selections will be recommended by the SERDP Executive Director to the
SERDP Council, which will approve the proposal within a reasonable
period of time after receipt in an effort to incorporate the work in to
the NGP. The Defense Supply Service -- Washington (DSSW) Contracts
Office, the contracting agency for the NGP, will make contract awards
within a reasonable period of time. The DSS-W point of contact is Ms.
Sally Williams, telephone (703) 693-5017. A Military Department of NIST
official will be designated a Contracting Officer's Technical
Representative (COTR) for each contract, as recommended by the NGP TPM.
It is the policy of the SERDP Program Office and the DSSW Contracts
Office to treat all proposals as competitive and proprietary
information and to disclose the contents only for the purpose of
evaluation. The Government may use selected support contractor
personnel as special resources to assist in administering the
evaluation of the proposals. These persons are restricted by their
contracts from disclosing the proposal information or using it for
other than performing their assigned administrative task. Contractor
personnel are required to sign non-disclosure statements. By submission
of your proposal, you agree that your proposal information may be
disclosed to these selected contractors for the limited purpose stated
above. Any information submitted with you proposal that you do not
consent to limited release to these contractors must be clearly marked
and submitted segregated from other proposal material. This
announcement constitutes a Broad Agency Announcement as contemplated in
FAR 6.102(d)(2). There will be no formal request for proposals or other
solicitations outside the Government regarding this announcement. The
Government reserves the right to select for award all, some, or none of
the proposals received in response to this announcement. The provisions
of DFARS subpart 227.71, Rights in Technical Data, will apply to any
award issued under this BAA. All responsible sources may submit a
proposal which shall be considered. Historical Black Colleges and
Universities (HBCU) and Minority Institutions (MI) are encouraged to
submit proposals and join others in submitting proposals; however, no
portion of this BAA will be set aside for HBCU and MI participation due
to the impracticality of reserving discrete or severable areas of NGP
technology for exclusive competition among these entities. (0028) Loren Data Corp. http://www.ld.com (SYN# 0001 19970131\A-0001.SOL)
A - Research and Development Index Page
|
|