COMMERCE BUSINESS DAILY ISSUE OF FEBRUARY 10,1997 PSA#1779354 Contracting Squadron/LGCC, 3112 Broadway Ave, Unit 5B, Eielson AFB,
Alaska 99702-1887 Z -- COMPOSITE POL FACILITY MAINTENANCE AND REPAIR SOL F65503-97-B0006
DUE 032797 POC Randy Hays, (907) 377-1838, Contract Administrator,
Eielson AFB, Alaska. Work shall include but is not limited to the
following: Repair Tank 15; Work includes the removal of residual fuel
and sludge from the tank and underground fuel piping, tank cleaning and
abandonment of underground fuel piping. For the tank, the work includes
the provision of above ground fuel piping, relocating the tank
approximately 200 feet and placing the tank on a new tank floor and
concrete ringwall foundation. The tank work also includes the
provisions for cathodic protection, leak detection, interior tank
coating modification, interior and exterior tank piping, overfill
alarms, gauge tube, overfill prevention valve and other incidental
work. For the tank dike, the work includes the provision of earth work,
a dike liner, a dike drain and other incidental work. Repair Tank 22;
Work includes the removal of residual fuel and sludge from the tank and
underground fuel piping, tank cleaning and abandonment of underground
fuel piping. For the tank, the work includes the provision of above
ground fuel piping, tank lifting, tank floor installation, concrete
ringwall foundation, cathodic protection, leak detection, interior and
exterior tank coating, interior and exterior tank piping, overfill
alarms gauge tube, overfill prevention valve and other incidental work.
For the tank dike, the work includes the provisions of earth work, a
dike liner, a dike drain, and other incidental work. Repair Tank 59;
Work includes the removal of residual fuel and sludge from the tank and
underground fuel piping, tank cleaning and abandonment of underground
fuel piping. For the tank, the work includes the provision of fuel
piping, a tank floor, cathodic protection, leak detection, interior and
exterior tank coating, interior and exterior tank piping, overfill
alarms, gauge tube, overfill prevention valve and other incidental
work. For the tank dike, the work includes the provision of earth work,
a dike liner, a dike drain and other incidental work. Repair Dikes E-6
Complex; The work includes the removal of residual fuel and sludge
from six (6) existing tanks and associated piping, tank cleaning, and
removal of underground fuel piping. For the tanks, the work includes
the provision of aboveground fuel piping from the facility valve house
to each tank, overfill alarm systems, gauge tubes, overfill protection
valves, and other incidental work. For the tank dikes, the work
includes the provision of earth work, dike drains and other incidental
work. Performance period shall be 1110 calendar days. SIC code is
1629. The magnitude is between $5,000,000.00 and $10,000,000.00. This
project will issue on or about 25 Mar 97. All requests for bid packages
must be submitted in writing to this office accompanied by a check or
money order payable to U.S. Treasury in the amount of $60.00. No
telephone or fax requests will be accepted. (0037) Loren Data Corp. http://www.ld.com (SYN# 0152 19970210\Z-0012.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|