COMMERCE BUSINESS DAILY ISSUE OF FEBRUARY 11,1997 PSA#1780SOUTHWESTNAVFACENGCOM (Code 0212), 1220 Pacific Highway, San Diego, CA
92132-5187 Y -- INSTALL SMI-COMDUCTOR PROCESSING EQUIPMENT, BUILDING 560 NORTH
(E22-96) SOL N68711-96-B-4229 DUE 041497 POC Contract Specialist,
Steven Miliner/Contracting Officer, Dorothy I. LeStage. PRESOLICITATION
NOTICE -- Part A: The work includes interior and exterior demolition.
Exterior demolition includes HVAC and mechanical systems, doors, stucco
walls, and associated appurtenances. Interior demolition includes stud
walls, doors, windows suspended ceilings, lighting, electrical
systems, fire sprinkler system, mechanical, process piping and
associated appurtenances. Interior demolition also includes removal of
resilient flooring, base, and mastic which contains asbestos. Exterior
work includes roofing, HVAC and mechanical systems, doors, stucco, and
related work. Interior work includes doors, windows, stud walls,
access flooring, conductive flooring, suspended ceilings, painting,
installation of government furnished equipment, lighting and electrical
systems, mechanical, process piping and related work. Interior work
also includes certification of Class 100 Cleanrooms and Class 1000
Cleanroom Chases, and ultrapure process piping system. Part B: The work
includes demolition of an acid neutralization system and related items.
The work includes an acid neutralization system with sump tanks, sump
pumps, acid neutralization tanks, alarm system, double wall piping, and
related eletrical work and incidental related work complete and ready
for use. -- The estimated cost is $1,000,000 to $5,000,000 -- Firm
Fixed Price Contract. -- Contract duration is approximately 120
calendar days. -- This proposed contract will be unrestricted. -- The
Standard Industrial Code is 1731 and the annual size standard is $7.0
million. It is recommended the subcontracting goals reflect a minimum
goal of 5% for Small Disadvantaged Business Subcontracting effort.
Bidders should request in writing stating IFB number N68711-96-B-4229,
with complete name, address, area code and phone number and whether
bidding as a prime/subcontractor/ supplier. -- Telephone requests will
not be accepted. -- There will be a charge for plans and specs that is
yet to be determined. The fee will be non-refundable. -- Mailrequests
with a check payable to DEFENSE PRINTING SERVICE to Southwest Division,
Naval Facilities Engineering Command (Plan Issue), 1220 Pacific
Highway, Bldg. 132, San Diego, CA 92132-5187 or fax requests to (619)
532-2083. -- Fax requests will be accepted but, WILL NOT be processed
until your check has been received by this office. -- Submit one (1)
check per project. -- Solicitation packages are limited to two (2) sets
per prime and one (1) set per subcontractor/supplier. -- Bidders
responding under this advertisement will not be required to resubmit
request once formally advertised. -- Tentative issue date is on or
about 14 March 1997 with an opening date of approximately 30 days later
(NOTE: BOD stated above is TENTATIVE). -- Responses are due no later
than 15 calendar days after publication of the advertisement in the
CBD. (0038) Loren Data Corp. http://www.ld.com (SYN# 0136 19970211\Y-0010.SOL)