COMMERCE BUSINESS DAILY ISSUE OF FEBRUARY 24,1997 PSA#1788U. S. Army Engineer District, Savannah, P.O. Box 889, Savannah, Georgia
31402-0889 C -- ADD/ALTER C-130 SQUADRON OPERATIONS AND AIRCRAFT MAINTENANCE
UNIT, TMKH953008 -- POPE AFB, NC POC Dan Lenz, 912/652-5585 The
following announcement appeared in the January 31, 1997 issue of the
Commerce Business Daily. PLEASE NOTE REVISION OF SELECTION CRITERIA
(5): Use of PACES. The estimates for this project shall be prepared
using the latest version of PACES. 1. CONTRACT INFORMATION: A-E
services are required for preparation of a Request for Proposals to
design and build two additions to an existing building, Option 1 --
serve on the review team for Technical Conformance of Proposals and
Option 2 -- Provide Construction Phase Services for Add/Alter C-130
Squadron Operations and Maintenance Unit, TMKH953008, Pope AFB, NC.
This will be a firm fixed price contract. The contract is anticipated
to be awarded in March 1997 and completed in July 1997. The estimated
construction cost range is less than $5,000.000. This announcement is
open to all firms, regardless of size. 2. PROJECT INFORMATION: The work
will be in three options. OPTION 1 -- The A-E will perform all
Architect-Engineer services necessary in preparation of Request for
Proposals to design and build two additions, one to each end of an
existing building. The additions will be 2,200 square meters and 2,050
square meters, totaling 4,250 SM. The successful firm will be given a
Customer Concept Document (CCD) developed by the Air Force. The CCD is
a booklet which outlines the project requirements. The A-E will utilize
this booklet to develop the Request for Proposals based upon Savannah
District criteria. OPTION 1 -- The A-E will serve on the review team
for Technical Conformance of Proposals. OPTION 2 -- After award, the
A-E will provide Construction Phase Services. 3. SELECTION CRITERIA:
See Note 24 for general A-E selection process. The selection criteria
are listed below in descending order of importance (firms by major
criteria and then by each sub-criterion). Criteria A thru E are
primary. Criteria F thru H are secondary and will only be used as
"tie-breakers" among technically equal firms. A. Specialized experience
and technical competence in: (1) Preparation of Requests for Proposals
for Design/Build contracts for industrial buildings; (2) Design of new
industrial buildings and addition to existing industrial buildings; (3)
Providing construction phase services; (4) Use of CADD; (5) Use of
PACES. The estimates for this project shall be prepared using the
latest version of PACES. The software and User's Manual will be
provided by the Savannah District free of charge to the successful A-E.
The drawings will be prepared using graphics created via
Intergraph/Bentley Microstation PC version 5.0 or later or Microstation
32. Drawings created using other CADD software must be translated to
the Microstation (*dgn) format. The Contractor will possess the
software to enable the full translation of drawing files. Before
selection, the pre-selected A-E's may be required to demonstrate the
above compatibility by reproducing a Government-supplied standard
drawing and translating it to the Intergraph/Bentley Microstation
format with proper leveling, line weights, symbology, color, etc. as
described in EM-1110-1-1807. Compliance with this requirement will be
submitted as part of the SF 255 submittal. B. Past performance on DoD
and other contracts with respect to cost control, quality of work, and
compliance with performance schedules. C. Capacity to accomplish the
work in the stated contract period and to dedicate at least one each of
the following disciplines: architectural, electrical engineer,
structural engineer, civil engineer, mechanical engineer. The design
team must include a Registered Engineer or Registered Architect who is
a full "member" in good standing of the Society of Fire Protection
Engineers (SFPE) or an individual who is a Registered Fire Protection
Engineer and whose principle duties are fire protection engineering.
Disregard the "to be utilized" statement at Block 4 of SF 255 and show
total depth of staff in all disciplines. D. Professional
Qualifications of key management and professional staff members.
Resumes (Block 7 of the SF 255) must be provided for these disciplines,
including consultants. E. Knowledge of Locality: Knowledge of locality
as it pertains in design and construction methods of projects in the
geographic area of this contract. SECONDARY CRITERIA: F. Small
Business, Small Disadvantaged Business, and Women Owned Business
Participation: Extent of participation of small business, small
disadvantaged businesses, women owned business, historically black
colleges and universities, and minority institutions in the proposed
contract team, measured as a percentage of the total estimated effort.
G. Equitable Distribution of DoD Contracts: Volume of DoD contract
awards in the last 12 months as described in Note 24. 4. SUBMISSION
REQUIREMENTS: See Note 24 for general submission requirements.
Interested firms must submit ONE (1) copy of SF 255 (11/92 edition) for
prime and ONE (1) copy of SF 254 (11/92 edition) for prime and all
consultants to the following address: U.S. Army Engineer District,
Savannah, ATTN: CESAS-EN-EA, 100 W. Oglethorpe, Savannah, GA 31401, not
later than the close of business on the 30th day after the date of this
announcement. If the 30th day is a Saturday, Sunday, or Federal
Holiday, the deadline is the close of business of the next business
day. NO FAXED SUBMITTALS WILL BE ACCEPTED. FIRMS MUST INCLUDE PRIME's
ACASS NUMBER in Block 3b of SF 255. For ACASS information call
503/326-3459. Cover letters and extraneous materials (Brochures, etc.)
will not be considered. PHONE CALLS are DISCOURAGED unless ABSOLUTELY
necessary. PERSONAL VISITS for the purpose of DISCUSSING this
announcement will NOT BE SCHEDULED. THIS is NOT a REQUEST for a
PROPOSAL. (0051) Loren Data Corp. http://www.ld.com (SYN# 0027 19970224\C-0004.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|