COMMERCE BUSINESS DAILY ISSUE OF MARCH 21,1997 PSA#1807314th Contracting Squadron, 642 Thomas Avenue, Little Rock AFB, AR
72099-5019 Z -- REPAIR PRIMARY POWER VAULT B-104, B-120 SOL F03602-97-B0003 DUE
053097 POC Contact SSgt Michael Bittner, (501) 988-3855, or Contracting
Officer, Loretta Zimmer, (501) 988-3379; Facsimile Number (501)
988-8119 The principle features of work for this project are, but are
not limited to: (a) Remove existing 2400 volt, single phase, airfield
lighting, constant current regulators and replace with new 480 volt
regulators; (b) Remove 4160 volt exposed bus and associated insulators
and fused cutouts; (c) Remove 4160 volt service to Bldg-120. Install
new parallel service from existing pole mounted transformers and served
from existing 13.8KV primary circuit; (d) Remove three 2400 volt oil
switches that serve beacon and strobe lights on each end of runway; (e)
Check current loads and verify size of transformer, emergency
generator, and service conductors; (f) Provide three new 480-2400 volt,
single phase, dry type transformers in vault to step 480 volts up to
2400 volts to serve existing beacon and strobe lights at each end of
runway. Replace existing underground cables between vault and riser
pole serving the beacon with new cables. Existing overhead conductors
wserving beacon will remain in service; (g) Replace existing oil filled
selector switch on approach lighting circuit; (h) Replace existing
airfield lighting control system with new computerized control and
monitoring system; (i) Upgrade existing vault ventilation system; (j)
Replace existing airfield lighting control system with new computerized
control and monitoring system; (k) Existing regulators that are
currently operating on 208 volt system will remain in service without
change; (l) Provide fire alarm system in vault that reports be radio to
Base fire alarm system; (m) Provide filters on vault outside wall
louvers to prevent dust from entering vault; (n) Provide a new 600
ampere, 120/208 volt, 3 phase main service panel, replacing the
existing 400 ampere panel, and connect all loads to the new main
service panel. This is a firm-fixed price contract. The estimated cost
of construction is between $500,000 and $1,000,000. The performance
period will be 180 days. This procurement is being issued on an
unrestricted basis with small disadvantaged business evaluation
preference. This office proposes to issue IFB F03602-97-B0003 on or
about 30 Apr 97. Only written rquests for solicitation packages will be
accepted. (0078) Loren Data Corp. http://www.ld.com (SYN# 0151 19970321\Z-0017.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|