COMMERCE BUSINESS DAILY ISSUE OF APRIL 2,1997 PSA#1815U.S. Army Engineer District, Alaska, PO Box 898, Anchorage, Alaska
99506-0898 Y -- HYDRANT FUEL SYSTEM (WEST RAMP), ELMENDORF AFB, ALASKA SOL
DACA85-97-B-0015 DUE 052297 POC Contact, Gail M. West,
907/753-2552/Contracting Officer, Thomas L. Carter, 907/753-2551
Description of work to be performed: Construct a new Type III 2,400
gallon-per-minute (GPM) hydrant fueling system with two 10,000 barrel
operating tanks and four hydrant outlets. The project includes a 2,400
GPM pumphouse with filter separators, HVAC control room, stainless
steel piping, valves, trenching, apron lighting, taxiway pavement,
fencing and connection to the existing base fuel distribution system.
The design will be in standard English units. Responders are advised
that the requirements may be delayed, cancelled or advised at any time
during the solicitation, selection, evaluation, negotiation, and/or
final award process based on decisions related to DOD changes and
disposition of the Armed Services. Range: Over $10,000,000 -- FFP --
420 days completion time -- Plans & spec fee: $140.00 -- SIC Code 1629.
OPEN TO LARGE AND SMALL BUSINESSES. (0087) Loren Data Corp. http://www.ld.com (SYN# 0077 19970402\Y-0001.SOL)
Y - Construction of Structures and Facilities Index Page
|
|