COMMERCE BUSINESS DAILY ISSUE OF APRIL 2,1997 PSA#1815SOUTHWESTNAVFACENGCOM, 1220 Pacific Highway, San Diego, CA 92132-5187 Y -- P-179 DECENTRALIZATION OF THE EXISTING CENTRAL STEAM AND
DISTRIBUTION SYSTEM SOL N68711-96-C-4557 DUE 052697 POC For Plans and
Specs info call 619-532-3725/Contract Specialist, Lucile
Miranda/Contracting Officer, Dorothy LeStage PRESOLICITATION NOTICE --
The work includes the provision of all labor, materials and equipment
for the decentralization of the existing central steam plant including
twenty-six (26) new gas fired steam and hot water boiler systems,
utility connections, modifications to existing HVAC systems, boiler
enclosures, demolition, removal and disposal of asbestos containing
materials, disconnection of building steam lines from existing steam
distribution system, connection of new boilers to existing buildings
and incidental related work. Coordination With Work of Other Contracts:
A new gas distribution system will be installed under a separate
contract. The scheduled completion of the gas distribution system is on
or before 01 April 1998. Cut over from the existing steam distribution
to the new boilers may begin as gas is available at individual boiler
locations. All boilers shall be operational within 30 days after
completion of the new gas distribution system and incidental related
work complete and readyfor use. -- The estimated cost is $1,000,000 --
$5,000,000. Firm Fixed Price Contract. -- Contract duration is
approximately 180 calendar days. -- This proposed contract will be
unrestricted. -- The Standard Industrial Code is 1623 and the annual
size standard is $17 million. It is recommended the subcontracting
goals reflect a minimum goal of 5% for Small Disadvantaged Business
Subcontracting effort. Bidders should request in writing stating IFB
number N68711-96-B-4557, with complete name, address, area code and
phone number and whether bidding as a prime/subcontractor/supplier. --
Telephone requests will not be accepted. -- There will be a charge for
plans and specs that is yet to be determined. The fee will be
non-refundable. -- Mail requests with a check payable to DEFENSE
PRINTING SERVICE to Southwest Division, Naval Facilities Engineering
Command (Plan Issue), 1220 Pacific Highway, Bldg. 132, San Diego, CA
92132-5187 or fax requests to (619) 532-2083. -- Fax requests will be
accepted but, WILL NOT be processed until your check has been received
by this office. -- Submit one (1) check per project. -- Solicitation
packages are limited to two (2) sets per prime and one (1) set per
subcontractor/supplier. -- Bidders responding under this advertisement
will not be required to resubmit request once formally advertised. --
Tentative issue date is on or about 25 April 1997 with an opening date
of approximately 30 days later (NOTE: BOD stated above is TENTATIVE).
-- Responses are due no later than 15 calendar days after publication
of the advertisement in the CBD. (0090) Loren Data Corp. http://www.ld.com (SYN# 0090 19970402\Y-0014.SOL)
Y - Construction of Structures and Facilities Index Page
|
|