COMMERCE BUSINESS DAILY ISSUE OF APRIL 15,1997 PSA#1824Phillips Laboratory, Directorate of Contracting, 2251 Maxwell Avenue
SE, Kirtland AFB, NM 87117-5773 A -- BROAD AGENCY ANNOUNCEMENT (BAA) SET-ASIDE FOR SPACE DEFENSE
RESEARCH BY HISTORICALLY BLACK COLLEGES AND UNIVERSITIES/MINORITY
INSTITUTIONS (HBCU/MIS) POC Debbie Chisenhall, Contract Specialist,
505/846-1326 This is Part Four of a Multi-Part Synopsis. .. (6) (c)
Status Report, DI-MGMT-80368 (quarterly, tailored to contractor's
format). Regarding all data deliverables, only the minimum necessary
data shall be proposed. The above required data is considered the
typical minimum requirement, other additional data may also be required
depending on the effort proposed. 3. SECURITY REQUIREMENTS: This
program is anticipated to be unclassified. 4. OTHER SPECIAL
REQUIREMENTS: (a) This acquisition is a 100 percent set-aside for
Historically Black Colleges and Universities (HBCUs)/Minority
Institutions (MIs) with eligibility as defined in DoD FAR Supplement
(DFARS) clause 252.226-7000. OFFERS FROM OTHER THAN HBCUs/ MIs ARE NOT
SOLICITED UNDER THIS ANNOUNCEMENT. Clauses 252.226-7000 and
252.226-7001 apply. The offeror must represent and certify, as part of
its offer, that it is a Historically Black College or University or a
Minority Institution as shown in DFARS provision 252.226-7001. A
HBCU/MI submitting an offer onits own name shall agree that at least 50
percent of the cost of the contract performance incurred for personnel
shall be expended for employees of the HBCU/MI. (b) Public Law 98-94
may be applicable to this program. Offerors must submit a DD Form 2345,
Export Controlled DoD Technical Data Agreement, to the Commander,
Defense Logistics Service Center, ATTN: DLSC-FBA, Federal Center,
Battle Creek, MI 49117-3084, 1-800-352-3572, for certification. The
offeror is required to submit a copy of the approved DD Form 2345,
including the required certification acceptance, to the Buyer with each
proposal unless the applicable Project Officer referred to by the focal
point agrees such certification is not required for the type effort to
be proposed. The Government reserves the right to require the
certification after proposal receipt even if initially not considered
applicable for the proposed effort. Failure to submit this
certification shall result in non-consideration for award if it is
determined to apply to the proposed effort. When applicable,
certification is required before contract award. Offerors shall certify
in their proposal that they will comply with all provisions of this
law. (c) International Trade in Arms Restrictions may apply. (d)
Proposals shall be valid for a period of not less than 180 days. 5.
ADDITIONAL INFORMATION. (a) Expected Award Date: Usually within 90 days
of proposal receipt but subject to change depending on funding
availability, etc. (b) Anticipated Type of Contract: Cost Reimbursement
-- No Fee utilizing the "Short Form Research Contract." (c) FAR clause
52.216-7 will be utilized in lieu of Advance Payments. (d)
Government-Furnished Property (GFP)/Contractor Acquired Property (CAP)
are not generally contemplated for this effort. If your proposal
incorporates requirements for materials, special test equipment,
special tooling, and/or agency peculiar property, strong justification
must be included which supports why it is in the government's best
interest to provide each of these proposed property items. Also, each
proposed property item must reflect the applicable type of property
category among the four acceptable categories shown above and how it
meets the FAR definition in FAR 45.101/45.301 for each category.
Proposals should reflect the policy that contractors are required to
furnish all property to perform government contracts since approval for
facilities (neither CAP nor GFP) is not contemplated; i.e., contractors
should not propose any property/equipment items which are not
materials, special test equipment, special tooling, and/or agency
peculiar property. (e) Individual contract awards are anticipated (but
not limited) to reflect the amounts shown for each requirement as
specified in each area subparagraph of the "Requirements" section
above. For example, a funding amount of $20K per year is expected to be
available for the total PL/LI requirement. However, as noted above,
PL's funding situation is not stable, and any award(s), if made, may be
significantly below or above the anticipated funding. (f) Note 26
applies: "Based upon market research, the Government is not using the
policies contained in Part 12, Acquisition of Commercial Items, in its
solicitation (i.e., this BAA, number 97-04) for the described supplies
or services. However, interested persons may identify to the
contracting officer their interest and capability to satisfy the
Government's requirement with a commercial item within 15 days of this
notice." 6. PROPOSAL PREPARATION INSTRUCTIONS: (a) In order that
proposals are afforded proper handling, offerors must mark their
proposals with the restrictive language stated in FAR 15.509(a) and
(b). (b) As appropriate, proposal questions should be directed to one
of the points of contact listed elsewhere herein. (c) A technical and
cost proposal, preferably submitted in separate volumes, is required.
(d) Proposals shall reference BAA number 97-03, shall identify the
applicable PL Directorate(s) and shall identify the subject area of the
proposal. (0101) Loren Data Corp. http://www.ld.com (SYN# 0006 19970415\A-0006.SOL)
A - Research and Development Index Page
|
|