|
COMMERCE BUSINESS DAILY ISSUE OF APRIL 15,1997 PSA#1824Bureau of Reclamation, Acquisition Operations Group, Code D-7810,
Denver Federal Center, PO Box 25007, Denver CO 80225 B -- STANDARD PENETRATION TEST ENERGY MEASUREMENT SERVICES SOL
1425-97-SQ-81-92035 DUE 042897 POC Evelyn M. Tate 303-236-8040 x228
WEB: Bureau of Reclamation Denver Office Acquisition Home Page,
http://www.usbr.gov/aamsden. E-MAIL: Contracting Officer's E-Mail
address, etate@do.usbr.gov. Concerns having the ability to furnish the
following services are requested to give written notification,
including a telephone number for a poc to the acquisition office listed
in this notice within 15 calendar days from the date of synopsis. The
Bureau of Reclamation has the following requirement: 1. Scope: This
Statement of Work (SOW) is for contracting of special Standard
Penetration Test (SPT) energy measurements. The contractor will develop
special instrumentation systems to measure energy at the top and bottom
of an long string of drill rods. Measurements will be taken in two
phases (May and September, 1997) at Terminus dam in California. Testing
will be performed at depths of 140 to 200 ft. The contractor will
analyze instrumentation data to determine energy content and losses on
the drill string during testing. This work is being performed for the
U.S. Army Corps of Engineers. 2. Location: Field work will be
performed at Terminus dam. Terminus dam is located on the Kaweah River,
about 21 miles east and upstream of the town of Visalia, Tulare County,
California. 3. Government furnished property, material, or service:
Reclamation will drill the pilot holes to the alluvium and will perform
the SPT testing for USACE at the project site. Reclamation will perform
these tests in accordance with ASTM D-1586 and D-6066. The SPT test
consists of drilling to the depth of interest and driving a 2-inch
sampler with a 140 lb hammer 1.5 ft. The number of blows, N, is counted
over the last 1 ft of penetration to determine the blow count N.
Reclamation will provide drilling rig(s), hammer systems, drill rods,
samplers. Reclamation will provide the drilling crew, consisting of a
driller and helper(s). The helpers can assist the contractor in general
labor requirements, i.e, moving equipment, placing rods, and other
duties as required. Reclamation will provide the contractor with a
short 2 -ft section of NWJ drill rods for the contractor to instrument,
if required. Reclamation will coordinate mobilization with the
contractor to assure that measurements can be obtained on all SPT
borings. Drilling will be performed on the downstream toe and upstream
face of the dam in 10 drill holes. The dam is operated by USACE. Site
access will be arranged by USACE. Contact person for the Corps is John
Nickell CESPK-ED-GD, Sacramento, CA. Reclamations contract technical
representative will be onsite during all testing. He will also review
draft reports for final approval. 4. Methods to be used: Drill rod
energy ratio, Eri, from the top transducer package will be measured in
accordance with American Society for Testing and materials standard
D-4633-86 (ASTM Annual Book of Standards, volume 04.08, 1994). Kc and
K1 factors should not be applied. Correction factor K2 will not be
required due to long rod length. The travel time to the return of the
reflective compression wave will be reported. This method is know as
the F2 approach. Drill rod energy ratio will also be determined using
the Force and Velocity method, where the product of force and velocity
shall be integrated over two different time periods. The integration
should be over the complete wave trace and the first pulse and return
(time = 2l'/c, where l' is length of rod and c is the compression
velocity in steel). By integrating only the first pulse, direct
comparison to F2 approach will be possible. 5. Specific Requirements:
5.a. Contractor experience -- the contractor should have experience
performing dynamic force and velocity measurements of both pile driving
and SPT drilling activities. These dynamic force and velocity
measurements are not easily performed. The data is recorded over a
period of milliseconds with high resolution data acquisition systems.
Operators of commercially available pile driving analyzing equipment,
may not have sufficient experience performing these measurements in SPT
testing, due to un-restrained nature of the drill rods and resulting
high frequency and high acceleration data. Previous work indicates
special accelerometers are required to obtain reliable data. The
contractor must demonstrate successful application of such equipment to
SPT testing through several published reports showing successful
results. Several practitioners have published data which does not show
true proportionality between force and velocity traces because of
their in-experience with dynamic measurement systems. The contractor
must provide a pretested instrumentation system which has proven to
deliver data with verifiable force and velocity under SPT drilling
conditions. Successful contractor should be able to demonstrate 5 years
experience in obtaining reliable force and velocity data in SPT
applications. 5.a. Phases -- there are five phases of the work; Phase
1. Prepare Instrumentation systems Phase 2. Perform measurements in 5
holes along the downstream toe May to June 1997. Phase 3. Analyze data
from Phase I, preliminary modeling tested. Phase 4. Perform
measurements in 5 drill holes on the upstream face of the dam. Phase 5.
Analyze data and report. 5.b. Tasks Phase 1 -- Construct two
instrumented subassemblies of a short section of NWJ drill rod. Contact
Reclamation to be sure rods types are the same. The instrumented
subassemblies will have a minimum of 2 strain gages and 2
accelerometers mounted in a diametrically opposed position. The bottom
subassembly will be located downhole just above the sampler barrel.
The bottom subassembly should be waterproofed and be supplied with
waterproof cable to reach to the surface. The bottom subassembly must
be capable of insertion through 3.75 inch inside diameter hollowstem
augers. The maximum hole depth will be 200 ft. The top subassembly will
contain the same instrument array as the bottom but does not require
long cabling and clearance requirements for the bottom assembly are not
required. The sub-assemblies should be calibrated in the laboratory to
show correct response to transient loads. This calibration should use
traceable force and acceleration standards (NIST standards). The
contractor must supply data aquisition equipment capable of 1)
displaying drill rod energy transmission for each hammer blow and 2)
capability of storing the complete time history record of force and
velocity for most of the blows of each SPT test. The data aquisition
equipment should have real time direct integration capability to report
drill rod energy as blows are being applied, such as paper tape or LED
readout. The data aquisition equipment must be specially designed for
Pile driving or SPT data aquisition and must have the following
capabilities; -- Automatic data storage -- Automatic data presentation
software -- Four strain channels -- Four acceleration channels
(piezoresistive or piezoelectric) -- Four velocity integrators --
Automatic balancing of signals -- Built in A/D converter, 8 channels at
up to 20Khz each. Once the instrumentation packages are ready, the
contractor should notify the contract technical officer so that field
drilling can be coordinated.Phase II -- The contractor will provide the
instrumentation systems and an experienced engineer for 5 days of field
measurements. Five drill holes will be drilled in the downstream
portion of the dam. The test depth is around 145 ft. Eight inch pilot
holes will be pre-drilled by Reclamation prior to arrival. These holes
will be backfilled with pea gravel. Re-drilling will be performed by
Reclamation with a rotary drill equipped with hollow-stem augers. The
hollow-stem augers will be advanced to the base of the pre-drilled
hole. Drill fluid will be added to the column in preparation for SPT
testing. SPT testing will be performed by Reclamation at 2.5 ft
intervals for approximately 20 to 30 ft of testing. SPT will be
performed by Reclamation in accordance with ASTM D-1586, and D-6066.
The blow count rate will be controlled by automatic hammer settings and
will likely be 40 blows per minute, but could range from 20 to 50 blows
per minute. Reclamation has not selected the drill for the SPT testing.
It is anticipated the drill may be a CME 85, 75 or Mobil B-61. The
contractors equipment must allow for normal conduct of the SPT by
Reclamation. This means the transducer and data collection system must
not interfere with the hammer drop system. Also, the contractor shall
supply cable reel systems and cable tie systems to expedite placement
of the sampler and rods. Since the alluvium is only 20 to 30 ft thick,
there will only be about 10 SPT tests performed by Reclamation on each
hole. Reclamation anticipates that one hole can be completed each day.
Since part of the day will be getting augers back down to depth, the
contractor can assume a good portion of each dam can be in standby
status. The duration of the field work will be 5 calender days.
Reclamation drill crews will work 10 hr days. The contractor will bill
mobilization and field labor costs as separate items. If Reclamation's
drill breaks down, the contractor will remain on site in a standby
status and will be reimbursed for this field cost. Thecontractor is
responsible for warning Reclamation drill operators of impending damage
to their equipment. During performance of the SPT the contractors field
engineer should evaluate the data and in consultation with the Contract
Technical Representative, decide on the necessary sampling rate for
storage of complete wave forms. The data aquisition equipment must be
capable of storing all data from a series of blows. At a minimum, at
least 3 blows of complete waveform data should be stored. It is
doubtful however, that complete waveforms will be stored for all blows.
Field integration of drill rod energy, as calculated from the top
transducers must be performed for all hammer blows in the test. The
foundation materials may be gravelly with N values over 50. In these
cases, reflected compression waves may occur. The contractors equipment
must be capable of recording an interpreting force and velocity data
for either tensile wave or compression wave returns. Phase 3 -- Interim
Report -- Prior to the fall mobilization, the contractor will issue a
report for review by the Contractor Technical Representative. The draft
report should be completed 4 weeks after the field testing. The report
should include the following elements; -- Summary of drill rod
energies from the top transducer as outlined in section 3. Three values
of Eri will be reported, F2, FxV (2l'/c), and FxV complete wave. This
data should be available for at least three blows of data for each SPT
test (approximately 50 tests). The report will include example wave
traces showing integration cutoff times. -- Evaluation of energy loss
by comparing the top and bottom load cells. The contractor must
evaluate energy losses in the first wave pulse and the complete wave
pulse.. -- Modeling -- The contractor should apply GRLWEAP and CAPWAP
modeling software to the SPT drill rod system. The model should be
tested on a ranges of depths tested . The model should then be extended
to predict energy losses at a 180 to 200 ft rod lengthcondition (fall
program). The Contract Officers Technical Representative (COTR) will
review the draft report with 2 weeks of issue. The contractor should
strive to resolve any questions or propose modifications to the
procedures used for next set of measurements (fall program). The
Contractor should finalize the interim report within 3 weeks of receipt
of COTR's review. Phase 4 On phase 4 another series of 5 drill holes
will be installed in the upstream face of the embankment. The depth
interval of testing will be 185 to 200 ft. This testing is expected to
occur in September or October of 1997. The contractor will coordinate
with Reclamation for the appropriate start date. The possibility
exists that a different drill and hammer system will be used on the
second round of drilling, but the same drill rods will be used. The
contractor will perform measurements on these holes over a period of 5
days. Reclamation estimates this testing duration as before, i.e., 5
holes in one week. See Phase 2 writeupfor sampling considerations. As
with Phase 2, all Phase3 work will in the field, Reclamation will
provide the drilling, and the contractor responsibilities are the same
as given under Phase 2. There may be a desire to change some operating
variables to test modeling procedures. For example, the automatic
hammer adjustment may be set differently to evaluate effects of lower
energy transmission. Or, shallower tests may be attempted. Phase 5 --
Final report. A final report should be issued to complete the Project.
The final report should include the same items in the Phase 3 interim
report as follows; -- Summary of drill rod energies from the top
transducer as outlined in section 3. Three values of Eri will be
reported, F2, FxV (2l'/c), and FxV complete wave. This data should be
available for at least three blows of data for each SPT test
(approximately 50 tests). The report will include example wave traces
showing integration cutoff times. -- Evaluation of energy loss by
comparing the topand bottom load cells. The contractor must evaluate
energy losses in the first wave pulse and the complete wave pulse. --
Modeling -- Discuss the differences in measured and predicted energy
losses in NWJ drill rod in the deeper holes in phase 4. Refine the
GRLWEAP and CAPWAP models for other drill rods. Predict the performance
of other commonly used drill rods such as A and B sizes. A draft report
shall be submitted to the COTR within 2 weeks of completion of phase 4
field testing. The COTR will review the draft report within 2 weeks of
draft submission. The contractor shall provide 10 copies of a final
report within 2 weeks of receipt of draft review comments. 6.
Deliverables Deliverables include Draft interim report and a final
report as outlined in Section 5, Phase 3 and 5. Delivery dates and
other details have already been given in section 5. 7. Time Schedule --
(ESTIMATED) Phase 1 -- May 16, 1997 Phase 2 -- June 2 through 6, 1997
Phase 3 -- August 1, 1997 Phase 4 -- Sept 15 through 19, 1997 Phase 5
-- Sept 22 through October 31, 1997 Comments on the time schedule.
Drill scheduling by Reclamation can be influenced by many factors. For
example, a safety of dams problem in another region can detain our
drill crews. The phase II drill measurements have been tentatively
scheduled for mid May. If the contractor can prepare the instrumented
sub quickly -- Phase II drilling can be scheduled for Mid May start. 8.
Inspection and Acceptance -- The COTR will provide the contracting
officer with inspection or acceptance reports. 9. Proposed Bid
Schedules and Partial Payments The following bidding schedule is
recommended a. Instrumentation Package development and calibration
Phase 1 -- lump sum b. Project mobilization -- Phase 2 -- lump sum c.
Travel and living Expenses -- Phase 2 -- Daily rate d. Field Staff day
cost for Project engineer -- Daily rate e. Draft Interim report Phase
3 -- lump sum f. Project mobilization -- Phase 4 -- lump sum g. Travel
and living Expenses -- Phase 4 -- Daily rate h. Field Staff day cost
for Project engineer 4 -- Daily rate I. Final Report -- Phase 5 -- lump
sum An invoice may be submitted after completion of Phase 3 and the
COTR will review for approval for payment. The contractor must not
initiate any work outside the scope of the initial agreement without
approval of the contracting officer. This is not a formal solicitation.
However, concerns that response shall provide detailed data concerning
their capabilities and may request to receive a copy of the
solicitation when and if it becomes available. This notice may
represent the only official notice of such a solicitation. (0100) Loren Data Corp. http://www.ld.com (SYN# 0025 19970415\B-0010.SOL)
B - Special Studies and Analyses - Not R&D Index Page
|
|