COMMERCE BUSINESS DAILY ISSUE OF APRIL 15,1997 PSA#1824USDA-Natural Resources Conservation Service, ATTN: Contracting Officer,
100 East B Street, Room 3124, Casper, WY 82601-1969 Y -- EARTHEN CONSTRUCTION OF COLLEGE PHASE -- ALLISON DRAW FLOOD
CHANNEL SOL NRCS-4-WY-97 DUE 052797 POC Sue Jones, Contracting Officer,
307-261-6468 College Phase of Allison Draw Flood Channel -- Earthen
Construction. Construction will consist of excavating and spoiling
approximately 183,300 cuyd, placing approx. 13,838 cuyd of rock riprap,
approx. 3726 cuyd of gravel bedding, topsoiling and seeding approx. 45
acres, and the construction of a headgate and check board system.
Project is located from approx. 650 feet east of Avenue C continuing
east to College Drive on the south side of Cheyenne, Wyoming.
Performance time is 144 calendar days. Estimated price range $500,000
to $1,000,000. Contractors submitting a bid for this project are
strongly urged to attend the site showing planned for May 13, 1997. All
responsible sources may submit a bid which will be considered by the
agency. IFB will be available o/a April 22, 1997. (0100) Loren Data Corp. http://www.ld.com (SYN# 0106 19970415\Y-0001.SOL)