|
COMMERCE BUSINESS DAILY ISSUE OF APRIL 17,1997 PSA#1826Administrative Procurement Branch, Environmental Protection Agency,
Fairchild Building -- 7th Floor, 499 S. Capital Street, S.W.,
Washington, DC 20024 B -- TESTING OF PROBES IN A NON-AXIAL FLOW SWIRL WIND TUNNEL SOL
DC0071 DUE 043097 POC Ms. Jones at 202-260-9031 WEB: NOT AVAILABLE, NOT
AVAILABLE. E-MAIL: NOT AVAILABLE, NOT AVAILABLE. This contract action
is for services for which the Government intends to solicit and
negotiate with only one source using the Simplified Acquisition
Procedures of FAR Part 13 to: perform the attached test matrix on from
8 to 11 probes to be provided by the WAM. Each test will involve a
16-point Method 1 traverse from four ports. Upon completion of testing,
the contractor shall ship all of the tested probes to Durham, North
Carolina to an address that wil be provided. The contractor shall
participate in periodic conference calls with EPA project managers to
discuss the testing status. The contractor shall participate in a
pre-test meeting for EPA project managers at the contractor's
facilities. The purpose of the pre-test meeting is to discuss the test
plan and to observe the start of swirl wind tunnel testing.
Deliverables/Schedule as follow: A. Task no. 1: Work Plan due: 15 days
of receipt of this work assignment B. Task no. 2: Hold pre-test
meeting due: Same day as testing starts C. Task no.3: Perform Testing
due: 2 weeks after receipt of probes D. Task no. 4: Data Analysis and
Report Preparation -- Interim QA'd data 2 weeks after testing -- Final
QA'd data 4 weeks after testing -- Draft technical memorandum 6 weeks
after testing -- Final technical memorandum 8 weeks after testing E.
Task no. 5: Participate in weekly conference calls. Test Matrix, EPA
Probe Evaluation Swirl Condition Pitch Condition Degrees Flow Ports
Points Total Probe 0 10 20 30 A B C Speed Used per Port Points Name
(TM-1) 70 sfps 5,6,7,8 4 16 EPA1 x x x x EPA2 x x x x EPA3 x x x x EPA4
x x x x EPA5 x x x x EPA6 x x x x EPA7 x x x x EPA8 x x x x EPA9 x x x
x EPA10 x x x x EPA11 x x x x Criterion #1: To avoid duplication of
government effort and cost, contractor must have previously tested at
least some of the probes to be used in EPA's 'Continuation of Flow
Reference Method Field Testing and Analysis' study. These previous
tests must have been at yaw angles of 10 0, 20'. and O' and velocities
of 50, 70 and 90 feet per second. Criterion #2: Contractor must have
access and capability of testing in a wind tunnel capable of creating
swirl flow conditions at controllable, pre-set anoles of yaw and pitch.
(Note: The flow within the tunnel must display the indicated yaw and
pitch characteristics. It is not acceptable to sli-nply orient the
probes at pre-set angles to the flow stream in a wind tunnel where the
flow is axial.) At a minimum, the now in the tunnel must be able to be
pre-set at separate settings of approximately 10 degrees, 20 and 30
degrees yaw, and 10', 20, and 30 degrees pitch. Criterion #3: The total
axial velocity in the tunnel must be able to be held over a range from
50 through 90 feet per second and be able to be verified to within +
2.0 fps by the pressure drop across the venturi. Criterion #4:
Contractor must be capable of complying with the attached statement of
work. A statement confirming this ability si-ned by an authorized
representative of the contractor sMI be sufficient evidence of
capability. The above criteria must be met before submitting packages
to: US EPA; 401 M Street, SW; Bid and Proposal Room -- 300 Fairchild;
mail code 3803F; Washington, DC 20460 -- Attn: Ms. Nel Jones -- Fax at
202-260-1929. (0105) Loren Data Corp. http://www.ld.com (SYN# 0019 19970417\B-0004.SOL)
B - Special Studies and Analyses - Not R&D Index Page
|
|