|
COMMERCE BUSINESS DAILY ISSUE OF APRIL 23,1997 PSA#1830US ARMY CORPS OF ENGINEERS, PORTLAND DISTRICT, PO BOX 2946, PORTLAND OR
97208-2946 C -- DESIGN/BUILD FOR ELK CREEK DAM SOL 021&&&-9704-0002 POC
Christopher Nielsen (503) 326-6419 (Site Code DACW57) The Portland
District, Corps of Engineers is seeking sources for a 2 phase design
build procurement for the Elk Creek Project. The work will include
providing a "fish passage corridor" through the Project. Elk Creek
Project is located at river mile 1.7 above the confluence with the
Rogue River, 26.5 miles north of Medford, Oregon. Construction on the
project was stopped by court injunction in fiscal year 1987, with the
dam at one-third its design height. Following a court of appeals
decision in April 1995, the Corps of Engineers has entered into a
two-phase plan of action for long term management of the project in its
uncompleted state. The first phase of the plan is to provide fish
passage through the project by partial removal of a section of the dam
or spillway and appropriate routing and treatment of the stream above,
below, and through the dam. Major Construction Features: Routing of the
stream through the dam will require demolition of approximately 50,000
cy of RCC concrete and approximately 15,000 cy of conventional
concrete. Routing of the stream and local grading will require
approximately 500,000 cy of cut and fill and approximately 15,000 cy of
rock excavation. The length of affected stream is approximately 4,000
feet. Bank protection may be required and may include as much as 50,000
cy of revetment. A stream flow training wall may be required and may
include as much as 14,000 cy of revetment and core materials. Some
structural, electrical, and mechanical may be required. Major Design
Considerations: The routing and treatment of the stream will require
hydrologic and geomorphic analysis with a fisheries oversight. The
purpose is to provide a fish passage corridor in a stream that is
designed to be geomorphically balanced as much as is reasonably
possible immediately following construction. Much of this analysis has
been conducted and more may be required for approval of the plans and
specifications. Other conventional design will be necessary to provide
demolition, rock excavation, earthwork, bank protection, and other
features. The contractor will be required to acquire the appropriate
permits for access and to conduct work in and near water. The in-water
work period is June 15 through September 15. Some species of fish may
be listed or proposed for listing as an endangered species. Interested
firms should submit a company brochure and a one page letter of
interest within 30 days of the publication of this notice. No personal
presentations will be allowed at this time. Please direct all
technical questions to Jeff Sedey at (503) 326-6129. (0111) Loren Data Corp. http://www.ld.com (SYN# 0015 19970423\C-0008.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|