COMMERCE BUSINESS DAILY ISSUE OF MAY 6,1997 PSA#1839SOUTHWESTNAVFACENGCOM, Camp Pendleton AFT, Code 531, 1220 Pacific
Highway, Building 127, San Diego, CA 92132-5187 Z -- REPAIR/REPLACE ROOFS AND PIPING, MARINE CORPS MOUNTAIN WARFARE
TRAINING CENTER (MCMWTC), BRIDGEPORT, CALIFORNIA SOL N68711-97-B-8311
DUE 070997 POC Dave Jackson/Contract Specialist, (619) 532-2338,
Katherine Luhmann/Contracting Officer, (619) 532-2796. PRESOLICITATION
NOTICE -- The work includes Part A: PE9728M -- BOQ's/BEQ's and Part B:
PE9731M -- Dining Halls. The work for both parts includes the
furnishing of all labor, approved materials, and equipment and
incidental related work required to complete the addition of new metal
sloped roofs over the existing flat roofs and the replacement of
equipment to each building boiler room with any additional incidental
related work. The BOQ's/BEQ's new roof addition will incorporate
standing seam metal roofs with underlayment over 6-inch x 16 ga. steel
decking supported by 6-inch x 16 ga. metal stud walls. Existing vents
and flues shall be extended and flashed for sloped metal roofs. New
gable and walls shall be constructed of 6-inch x 16 ga. metal sutds
with 4-inch E.F.I.S with a secondary weather barrier over 1/2-inch
water resistant gypsum wallboard. Remove existing roof hatch panels and
replace panel with a removal E.F.I.S. lay-in panel. Provide insulation
of walls. Flashing and metal louver vents shall match existing
building base colors. The repair and replacement of equipment at the
BOQ's and BEQ's boiler rooms shall relate to domestic hot water and
heating systems for the buildings. All piping and electrical work to
support domestic hot water system modifications. Included is the
addition of concrete equipment pads and reinforcement of supports. The
Dining Hall Facility roof addition will also be that of a standing
seam roof over steel decking supported by metal stud walls. At new
vertical walls, flashing and wall finishes from existing roof structure
are to match existing. At the existing north roof, a removable roof
panel section is to be constructed. The existing stnading seam roof is
rolled to the side and then rolled back into place. All electronic
roof top devices are to relocate to top of the new roof. The repair and
replacement of equipment at the Dining Hall boiler room shall be the
domestic storage tanks, boilers and piping assoicated with the
equipment. The removal of the two 5.5 foot x 12-foot storage tanks
shall be through the removable section of roof by means of a crane.
Included is the addition of concrete equipment pads and reinforcements
to supports. -- The estimated cost is between $1,000,000 and
$5,000,000. -- Firm Fixed Price Contract. -- Contract duration is
approximately 180 calendar days. -- This proposed contract will be
unrestricted. -- The Standard Industrial Code is 1761 and the annual
size standard is $7 million. It is recommended the subcontracting goals
reflect a minimum goal of 5% for Small Disadvantaged Business
Subcontracting Effort. Bidders should request in writing stating IFB
number N68711-97-B-8311, with complete name, address, area code and
phone number and whether bidding as a prime/subcontractor/supplier. --
Telephone requests will not be accepted. -- There will be a charge for
plans and specs that is yet to be determined. The fee will be
non-refundable. -- The only methods of payment that will be accepted
for plans and specifications are Visa, Mastercard, cashiers cehcks or
money orders and they should be made out to DEFENSE PRINTING SERVICE.
-- Mail requests to Southwest Division, Naval Facilities Engineering
Command (Plan Issue), 1220 Pacific Highway, Building 132, San Diego, CA
92132-5187. -- Fax requests will be accepted but, WILL NOT be processed
until your method of payment has been received by this office. --
Solicitation packages are limited to two (2) sets per prime and one (1)
set per subcontractor/suppliers. -- Bidders responding under this
advertisement will not be required to resubmit request once formally
advertised. -- Tentative issue date is on or about 9 June 1997 with an
opening date of approximately 30 days later (NOTE: BOD stated above is
TENTATIVE). -- Responses are due no later than 15 calendar days after
publication of the advertisement in the CBD. (0122) Loren Data Corp. http://www.ld.com (SYN# 0116 19970506\Z-0033.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|