COMMERCE BUSINESS DAILY ISSUE OF MAY 9,1997 PSA#1842US Army Engineer District, Honolulu, Building 230, Attn: CEPOD-CT, Fort
Shafter, HI 96858-5440 C -- DESIGN OF POWER PLANT SOL DACA83-97-R-0025 DUE 051297 POC Mr.
Harold Nakaoka (808)438-0021 E-MAIL: click here to contact Contract
Specialist via e-mail, jenny.yatsushiro@pod01.usace.army.mil.
Architect-Engineer Services. Design of FY99 MCA PN 33149 Power
Plant-Roi Namur, Kwjalein Atoll, Marshall Islands 1. CONTRACT
INFORMATION: Architect-Engineer services, procured in accordance with
PL 92-582 (Brooks A-E Act) and FAR Part 36, are required for the design
of an electric power generating plant and various construction phase
services (base and options). This announcement is open to all
businesses regardless of size. A firm-fixed-price contract will be
negotiated. The contract is anticipated to be awarded in November 1997.
The selected firm will be required to obtain Defense Base Act insurance
(workman's compensation insurance) for work performed outside the
United States. The selected firm, if a large business firm, must comply
with FAR 52-219-9 regarding the requirement for a subcontracting plan
on that part of the work it intends to subcontract. The subcontracting
goals for this contract are that a minimum of 50% of the contractor's
intended subcontract amount be placed with small business (SB), which
includes small disadvantaged businesses (SDB), and 30% be placed with
SDB. The subcontracting plan is not required with this submittal but
the successful large business firm must submit an acceptable plan
before any award can be made. 2. PROJECT INFORMATION: Design of an
electric power generating plant and associated improvements. The power
plant capacity is estimated to be 13,500 KW. Associated improvements
include building to house the power plant and
administrative/operation/maintenance staff functions, paving, fencing,
fire protection, sewer, water, storm drainage and information system
utilities, demolition of existing structures (fuel tanks, buildings,
and utilities) and asbestos removal. Limited construction phase
services may be required, such as site visits or inspections during
construction, submittal reviews, attendance at selected construction
conferences, etc. The estimated construction cost is between
$25,000,000 and $100,000,000. Design must be prepared with metric
system of measurements and with CADD. Cost estimates must be prepared
using the Corps of Engineers Micro Computer Aided Cost Estimating
System (MCACES). 3. SELECTION CRITERIA: See Note 24 for general
selection process. The PRIMARY selection criteria in descending order
of importance are: (a) professional qualifications of the firm's
staff/consultants to be assigned to the projects; (b) specialized
experience of the firm in design of power plants; (c) the firm's past
performance on DoD and private sector contracts (cost control, quality
of work, compliance with schedule); (d) knowledge of the locality of
the projects; (e) capacity of the firm to accomplish work in the
required time (size of firm, workload, etc.); and (f) demonstrated
success in prescribing the use of recovered materials and achieving
waste reduction and energy efficiency in facility design. The SECONDARY
selection criteria in descending order of importance are: (a) location
of the firm; (b) volume of recent DoD work; and (c) participation of
SB, SDB, historically black colleges and universities, and minority
institutions in the proposed contract team, measured as a percentage of
the estimated effort. Offeror must provide adequate documentation in
blocks 7g and 10 of the Standard Form 255, Architect-Engineer and
Related Services Questionnaire for Specific Project, to illustrate the
extent of participation of the above-mentioned groups in terms of the
percentage of the total anticipated contract effort. 4. SUBMISSION
REQUIREMENTS: Firms desiring consideration must submit a Standard Form
255 no later than 4:00 p.m., Hawaiian Standard Time, by the due date
shown above or within thirty (30) calendar days from date of this
announcement, whichever is later. Should the due date fall on a weekend
or holiday, the submittal package will be due the first workday
thereafter. All responding firms must also include completed Standard
Form 254 for themselves and their subconsultants, if not already on
file with the Pacific Ocean Division. Submittals will be sent to U.S.
Army Engineer Division, Pacific Ocean Division, Bldg 230, Room 202,
ATTN: Ms. S. Kim, Fort Shafter, Hawaii 96858-5440. Small and
disadvantaged firms are encouraged to participate as prime contractors
or as members of joint ventures with other small businesses. All
interested contractors are reminded that the successful contractor will
be expected to place subcontracts to the maximum possible extent with
small and disadvantaged firms in accordance with the provisions of
Public Law 95-507. For further information regarding this proposed
acquisition, telephone (808) 438-0021. Request for Proposal No.
DACA83-97-R-0025 shall be utilized to solicit a proposal from the firm
selected. This is not a request for a proposal. (0127) Loren Data Corp. http://www.ld.com (SYN# 0016 19970509\C-0006.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|