COMMERCE BUSINESS DAILY ISSUE OF MAY 21,1997 PSA#1850Tennessee Valley Authority, Procurement, 1101 Market Street,
Chattanooga, TN 37402 Y -- MAINTENANCE AT JOBSITE DUE 061697 POC Contracting Officer, David
e. Ulmer, Phone: 423-751-3607, Fax: 423-751-7606 E-MAIL: David E.
Ulmer, deulmer@tva.gov. The Tennessee Valley Authority (TVA) plans a
grouting program for remediation of rim leakage at Tims Ford Dam. The
program includes drilling and grouting in karstic limestone rock to a
depth of about 100 feet. There are well defined but irregular seepage
paths containing significant velocities of seepage. TVA anticipates
using various cementitious grouts for the treatment. Tims Ford Dam is
located on the ELK River in middle Tennessee near the town of
Winchester. The grouting will begin the first of October, 1997, and
must be completed by the end of December, 1997. (0136) Loren Data Corp. http://www.ld.com (SYN# 0112 19970521\Y-0002.SOL)
Y - Construction of Structures and Facilities Index Page
|
|