COMMERCE BUSINESS DAILY ISSUE OF JUNE 3,1997 PSA#1858SOUTHWESTNAVFACENGCOM, Camp Pendleton AFT, Code 531, 1220 Pacific
Highway, Building 127, San Diego, CA 92132-5187 Z -- REPAIR/REPLACE ROOFS AND PIPING, MARINE CORPS MOUNTAIN WARFARE
TRAINING CENTER (MWMWTC), BRIDGEPORT, CALIFORNIA SOL N68711-97-B-8311
DUE 071797 POC Maria Macam/Contract Specialist, (619) 532-3282,
Katherine Luhmann/Contracting Officer, (619) 532-2796. DESCRIPTION OF
WORK -- The work includes Part A: PE9728M -- BOQ's/BEQ's and Part B:
PE9731M -- Dining Halls. The work for both parts includes the
furnishing of all labor, approved materials, and equipment and
incidental related work required to complete the addition of new metal
sloped roofs over the existing flat roofs and the replacement of
equipment to each building boiler room with any additional incidental
related work. The BOQ's/BEQ's new roof addition will incorporate
standing seam metal roofs with underlayment over 6-inch x 16 ga. steel
decking supported by 6-inch x 16 ga. metal stud walls. Existing vents
and flues shall be extended and flashed for sloped metal roofs. New
gable and walls shall be constructed of 6-inch x 16 ga. metal studs
with 4-inch E.F.I.S with a secondary weather barrier over 1/2-inch
water resistant gypsum wallboard. Remove existing roof hatch panels and
replace panel with a removal E.F.I.S. lay-in panel. Provide insulation
of walls. Flashing and metal louver ventsshall match existing building
base colors. The repair and replacement of equipment at the BOQ's and
BEQ's boiler rooms shall relate to domestic hot water and heating
systems for the buildings. All piping and electrical work to support
domestic hot water system modifications. Included is the addition of
concrete equipment pads and reinforcement of supports. The Dining Hall
Facility roof addition will also be that of a standing seam roof over
steel decking supported by metal stud walls. At new vertical walls,
flashing and wall finishes from existing roof structure are to match
existing. At the existing north roof, a removable roof panel section is
to be constructed. The existing standing seam roof is rolled to the
side and then rolled back into place. All electronic roof top devices
are to relocate to top of the new roof. The repair and replacement of
equipment at the Dining Hall boiler room shall be the domestic storage
tanks, boilers and piping assoicated with the equipment. The removal
of the two 5.5 foot x12-foot storage tanks shall be through the
removable section of roof by means of a crane. Included is the addition
of concrete equipment pads and reinforcements to supports. -- The
estimated cost is between $1,000,000 and $5,000,000. -- Firm Fixed
Price Contract. -- Contract duration is approximately 200 calendar
days. -- Bids will be considered from all responsible sources. -- This
project is unrestricted. -- The Standard Industrial Code is 1761 and
the annual size standard is $7 million. It is recommended the
subcontracting goals reflect a minimum goal of 5% for Small
Disadvantaged Business Subcontracting Effort. -- A site visit is
scheduled for 1 July 1997 from 9:30 a.m to 11:00 a.m. Please contact
Lt. Robert Fairbanks at 619-932-7761 if you would like to attend. --
NOTE: Plans and specs will not be mailed to firms within a 20 mile
radius of the issuing office. A fee will be charged for all plans and
specs that is yet to be determined. Please call the PLAN ISSUE office
at 619-532-2082 for the price of this project. -- Solicitation packages
may be acquired in person from Plan Issue or by mail. -- Telephone
requests will not be accepted. -- Requests for the solicitation package
must be in writing stating IFB number N68711-97-B-8311, with complete
name, address, area code and phone number and whether bidding as a
prime/subcontractor/supplier. -- Plan holders lists will not be faxed.
-- Mail requests to Southwest Division, Naval Facilities Engineering
Command (Plan Issue, Code 57CS.PI), Building 132, 1220 Pacific Highway,
San Diego, CA 92132-5187. The only methods of payment that will be
accepted for plans and specifications are Visa, Mastercard, cashiers
checks or money orders and they should be made out to DEFENSE PRINTING
SERVICE. -- Fees are not refundable. -- If you choose to pay by
cashiers check or money order, please submit one (1) cashiers check or
money order per project. -- Solicitation packages are limited to two
(2) sets per prime and one (1) set per subcontractor/suppliers. --
Plans and Specifications will be available on or about 17 June 1997.