COMMERCE BUSINESS DAILY ISSUE OF JUNE 19,1997 PSA#1870U.S. Army Corps of Engineers, Philadelphia Wanamaker Building, Room
643, 100 Penn Square East, Philadelphia, Pennsylvania 19107 Y -- DESIGN AND CONSTRUCT VISITING OFFICERS QUARTERS, DOVER AFB, DE
SOL DACA61-97-R-0017 DUE 080597 POC Ms. Jennifer Ward, Contract
Specialist, 215- 656-6773 17. This acquisition will be a one step
turnkey design and construction of a new 6,000 square meter three story
Visiting Officers Quarters (VOQ). The facility will be located in the
southern part of the base at 14th and Sumner Streets. Work includes,
but is not limited to, providing adequate living quarters to
accommodate temporary duty personnel, separate
mechanical/electrical/communication utility building, parking areas and
demolition of one substandard VOQ including asbestos removal and
disposal. This project will also include six options: Option 1 --
Demolition of two substandard VOQs including asbestos removal and
disposal; Options 2, 3 and 4 -- Additional guest rooms; Option 5 --
Soil testing and bioremediation or removal of petroleum contaminated
soils; Option 6 -- Disposal of asbestos (>2%) contaminated soil at
areas where HTHW Line is removed. Major evaluation criteria in
descending (weighted) order will include: Price Evaluation (50%),
Performance Capability (30%) and Technical Approach (20%). A more
detailed evaluation criteria will be included in the RFP package. Award
of the contract will be made as a whole to the offeror whose proposal
conforms to all requirements of the specifications and offers the
"greatest value" to the Government. The Standard Industrial
Classification (SIC) Code for this project is 1522 with a size standard
of $17.0 million. A Request for Proposal (RFP) package will be
available on or about 03 July 1997 at a cost of $25.00 a set. All
requests for the RFP package should be in writing along with a check or
money order made payable to "FAO, USAED, Norfolk" and must include your
Federal Tax Identification or Social Security Number. Payment will not
be refunded and specifications need not be returned. Please provide a
physical street address, telephone and fax number. Proposal are due by
close of business 05 August 1997. Completion time for this project is
713 calendar days. Estimated cost range is over $10,000,000.00. The RFP
will include criteria and specifications for the design and
construction of the facility; detailed requirements for submitting
proposals; and evaluation procedures. Affirmative action to ensure
equal opportunity is applicable to the resulting contract. Liquidated
damages will be specified. Davis Bacon rates will be applicable to the
construction portion and bonding will be required. This procurement is
unrestricted and subject to the availability of funds. SPECIAL NOTE:
All responders are advised that this requirement may be canceled or
rescinded at any time during the solicitation, selection, evaluation,
and/or final award process based on decisions related to DOD changes in
force structure and disposition of US Armed Forces.***** (0168) Loren Data Corp. http://www.ld.com (SYN# 0098 19970619\Y-0023.SOL)
Y - Construction of Structures and Facilities Index Page
|
|