COMMERCE BUSINESS DAILY ISSUE OF JULY 3,1997 PSA#1880U.S. Department of Energy, Western Area Power Administration, P.O. Box
6457, (615 S. 43rd Ave.), Phoenix, AZ 85005 Y -- PARKER AND DAVIS SUBSTATIONS OIL SPILL CONTAINMENT SOL
DE-FB65-97WG30544 DUE 082697 POC Lary A. Martin, Contract Specialist,
(602) 352-2646, John Rynerson, Contracting Officer, (602) 352-2504
Contractor shall provide all labor, material, and equipment necessary
to construct earth berms, placing earth blanket lining, excavating and
oil containment sump, installing geotextile, repairing subsidence
damage to switchyard surface, constructing membrane lining system at
three switchyards for Davis Dam and three switchyards for the Parker
Dam. Unrestricted solicitation. All responsible bidders will be
considered. Estimated cost of the project is between $250,000 and
$500,000. Period of Performance: All work shall be completed 180 days
after award. Place of Performance: Parker and Davis Substations work is
at two locations: (1) Davis Dam approximately 5 miles north of the town
of Bullhead City located in Mojave County, Arizona, and (2) Parker Dam
approximately 1 mile north of the town of Parker Dam in San Bernardino
County, California. Requests for the IFB should be mailed to the
Department of Energy at the above address or faxed to (602)352-2483
attention Lary Martin. The bid package will be available at no charge
on/about July 25, 1997. All requests for this solicitation MUST be
submitted in writing. Information Hours: 8:00am -- 3:00pm (ST) Monday
thru Friday.***** (0182) Loren Data Corp. http://www.ld.com (SYN# 0138 19970703\Y-0038.SOL)
Y - Construction of Structures and Facilities Index Page
|
|