COMMERCE BUSINESS DAILY ISSUE OF JULY 22,1997 PSA#1892Officer in Charge of Construction, Naval Air Station Atlanta, Bldg. 70,
1000 Halsey Ave., Marietta, GA 30060-5099 Y -- INSTALL 400 HZ CONVERTER, BUILDING 1 RAMP, NAS ATLANTA, MARIETTA,
GA SOL N62467-97-B-3262 DUE 090597 POC Point of Contact -- Contact
Linda Doerner, (770) 919-6513, Contracting Officer, Marsha Tyson, (770)
919-6686 E-MAIL: Officer in Charge of Construction, Naval Air Station
Atlanta, Marietta, GA, 62645077@eln.attmail.com. The work includes
providing all labor and material to install one (1) power pole, 3-phase
overhead primary, 3-phase underground direct burial primary, concrete
pad, pad mounted transformer, a 400 HZ solid state frequency converter,
and incidental related work, complete and ready for use. Completion
time will be 150 calendar days. Construction range between $100,000 --
$250,000. IFB will be available on or about August 5, 1997. Fax
requests to (770) 919-6800. Include Federal Express Account Number for
Priority Handling. Funds are presently not available for this project.
This project is issued pursuant to PL 104-208, Small Business
Competitiveness Demonstration Program (Unrestricted). (AC0717031-10)
(0198) Loren Data Corp. http://www.ld.com (SYN# 0146 19970722\Y-0017.SOL)
Y - Construction of Structures and Facilities Index Page
|
|