COMMERCE BUSINESS DAILY ISSUE OF OCTOBER 16,1997 PSA#1952Department of the Air Force, 436 Contracting Squadron, 639 Atlantic
Street, Dover AFB, DE 19902-5639 J -- REPAIR OF MAINTENANCE STANDS SOL F0760398R6001 DUE 102897 POC
Sheila Waddell, Contract Specialist, 302 677-5216 E-MAIL: SHEILA
WADDELL, waddel@lgc436.dover.af.mil. This is a modification to the
initial CBD Notice issued on 8 Oct 97. The scope of this project
requires following clause be added FAR at 52.211-12, Liquidated
Damages-Construction. (APR 1984) ALTERNATE 1 (APR 1984). (a) If the
Contractor fails to complete the work within the time specified in the
contract, or any extension, the Contractor shall pay to the Government
as liquidated damages, the sum of $81.58 dollars per day per phase not
completed or accepted by the government inspector as specified by date
due. (0287) Loren Data Corp. http://www.ld.com (SYN# 0035 19971016\J-0015.SOL)
J - Maintenance, Repair and Rebuilding of Equipment Index Page
|
|