|
COMMERCE BUSINESS DAILY ISSUE OF DECEMBER 23,1997 PSA#1998U.S. Army Engineer District, Alaska, Attn: CENPA-CT-CO-M, P.O. Box 898,
Anchorage, AK 99506-0898 (Physical Address: Bluff and Plum Streets,
Building 21-700 (Room 200), Elmendorf AFB, AK 99506-0898) Y -- REPLACE FUEL TANKAGE, ELMENDORF AFB, ALASKA SOL DACA85-98-B-0003
DUE 021798 POC Gail M West, (907)753-2552/Contracting Officer, Corps
of Engineers The design package is composed of two authorized projects:
(I) FY98 Replace Fuel Tankage -- Construct 3 new 13250 m3 (83.3k
barrel) aboveground welded steel jet fuel (jp-8) bulk storage tanks
with impervious dikes; a 300 mm nominal diameter (DN 300), 1800 meter
long receipt pipeline (Valve Pit 11N to the new bulk storage); a POL
pumphouse/operations building; a DN 200, 190 meter long issue fuel
line; a truck fill stand, site improvements including pavements and two
access roads, utilities, security fencing and lights. This system must
be capable of simultaneously receiving and issuing 76 LPS (1200 gpm).
Demolish four aboveground (25k barrel) North Jet Fuel Tanks and two
aboveground (20k barrel) South Jet Fuel Tanks. (II) FY97 Install 12"
(DN300) and Construct 10" (DN250) POL Pipelines -- The "Install DN 300
POL Pipeline" adds 1600 m of direct bury DN 300 receipt pipe to the
project (Valve Pit 13 to Valve Pit 11N). This additional DN300 pipeline
replaces an old DN200 pipeline segment. Pig launchers and receivers are
included as part of this project. The "Construct DN250 POL Pipeline"
adds 2400 m of direct bury DN250 issue pipe to the project. The pipe
will be constructed adjacent to the new DN300 receiving line and will
connect the new bulk fuel storage tanks to the West Ramp Hydrant Fuel
System at valve pit 17. Connecting points for two future hydrant fuel
systems in the North Ramp area will also be provided. These sections of
pipe will be bid as a separate item due to funding requirements.
Responders are advised that the requirements may be delayed, cancelled
or revised at any time during the solicitation, selection, evaluation,
negotiation, and/or final award process based on decisions related to
DOD changes and disposition of the Armed Services. Range: Over
$10,000,000 -- FFP 730 days completion time -- Plans & Spec fee:
$127.00 -- SIC Code 1629. OPEN TO LARGE AND SMALL BUSINESSES. (0353) Loren Data Corp. http://www.ld.com (SYN# 0108 19971223\Y-0009.SOL)
Y - Construction of Structures and Facilities Index Page
|
|