COMMERCE BUSINESS DAILY ISSUE OF JANUARY 14,1998 PSA#2011US ARMY CORPS OF ENGINEERS, NEW YORK DISTRICT, Attn: CENAN-CT, 26
Federal Plaza, Rm 1843, New York, N.Y. 10278-0900 Y -- DESIGN AND BUILT LOW NOX EMISISON CONTROL PROJECT PICATINNY
ARSENAL, DOVER NEW JERSEY SOL DACA51-98-R-0012 DUE 012298 POC Ina J.
Ohrwashel, 212-264-0154 Contract Specialist. Project Designn and Built
LOW NOx Emission Control Project Picatinny Arsenal, Dover NJ The
project consists of the design and retrofit of low NOx burner systems
and the addition of flue gas recirculation to two (2) 240 million BTU
per hour dual fuel (No. 6 oil and natural gas) boilers. The project
includes the removal of existing systems, and the design and
installation of four (4) burner assemblies per boiler, the installation
of flue gas recirculation systems for each boiler, replacement of
forced draft fans, burner management systems, fuel trains, fuel and
combustion instrumentation and controls. The value of this project is
estimated between $2,000,000 and $5,000,000. FAR 36.3 -- Two Phase
Design-Build Selection Procedures will be used in the Contractor
selection process. Phase One qualification is open to all interested
firms. After Qualification Statements for Phase One are submitted, the
United States Army Corp. of Engineers (USACE) will select a maximum of
five qualified offerors. to continue with Phase Two The following
evaluation factors will be used to evaluate Phase One qualification
statements. Factors are listed in decending order of importance.
1.Offeror's Technical Qualifications 2. Proposed Nox Burner Technology,
3.Offerors Financial Strength, 4. Experience With Same Burner
Technology and Size. 5. Offeror's Experience on Similar Projects. 6.
Offeror's Resource Availability, 7. Offeror's Organizational Structure,
8. Offeror's Key personnel Assignment, 9. Offeror's Quality Control
Procedure. No cost no price related information is required nor allowed
under Phase One Submittal. In Phase Two, no more than five qualified
offerors will be required to prepare and submit a technical proposal
which includes a conceptual (30%) design and a cost proposal for the
burner system retrofit design and construction based on design
criteria, specifications and diagrams prepared by USACE. The installed
and operating burner systems shall conform to approved detailed
design, installation, and burner performance specifications, and to
meet or exceed the New Jersey Department of Environmental Protection
(NJDEP) air regulatory permits for this project. In Phase Two,
solicitation documents will provide the complete statement of work..
Project acceptance criteria will include emission and combustion
performance testing and analysis to verify compliance. The work is to
conform with a project schedule where one of the project boilers is
available without disruption to provide the facility's steam supply.
The current project schedule calls for design to be complete during the
fourth quarter of calendar year 1998. Release for construction,
equipment procurement, and prefabrication are to be performed the first
quarter of calendar year 1999. The two boilers are to be sequentially
completed, operational and ready for acceptance testing by the fourth
quarter calendar year 1999. Only one of these boilers will be permitted
to be off line at any time. Contractor shall complete acceptance
testing and obtain USACE project acceptance by first quarter calendar
year 2000. Contractor responsibilities will also include providing
operation and maintenance manuals and boiler operator training. The
successful offeror will be required to provide the following services:
(A) DESIGN -- 60% design submission, 95% design submission, and 100%
design submission of Final Construction Documents and assistance with
the final plan check and approval. Provide design drawings in AUTOCAD
Release 12 or later format. (B) CONSTRUCTION -- The Contractor will be
required to construct the USACE/Low NOx Emission Control Project
completely and in accordance with the approved Final Construction
Documents, including required submittals, furnishing of all required
materials, equipment and personnel. The Contractor shall manage,
administer, supervise and inspect the construction. The coordination
and superintendence of all work shall be the responsibility of the
Contractor. The Contractor shall be responsible to develop burner
emissions and performance testingprotocols acceptable to both the USACE
and NJDEP, to conduct actual testing, prepare and formally submit test
results to USACE, receive approvals from USACE. SUBMISSION OF
QUALIFICATION STATEMENT: Phase One Request for Qualifications package
DACA51-98-R-0012 will be available on or about 22 January 1998 on the
New York District Web Site www.nan.usace.army.mil/intra/index.htm#CBD..
This package is only available on the forementioned website. Complete
submittal instructions for Phase One are contained in this package. The
Phase One qualification statement will be due on or about 21 February
1998. The Qualification Statement shall not be more than 75 pages. (1
original, 6 copies) Delivery by the prescribed time is to be made to:
Ms Ina J. Ohrwashel, Room 1843. Any changes to Request For
qualifications statement will be posted on the Website. There is will
be a non-refundable cost of $200.00 for all solicitation documents in
Phase Two. If you desire drawings and solicitation for this project,
please send your request along with your non-refundable remittance made
payable to: FAO,USA,COE, NED Note that Phase One Solicitaiton document
consist only the Request for Qualfication Packet. There will be no
other CBD synopsies of this project.. This project is unrestricted and
all qualified firms may submit a Phase One Qualification Statement.