COMMERCE BUSINESS DAILY ISSUE OF JANUARY 20,1998 PSA#2014Bi-State Development Agency, 707 North First Street, St Louis, Missouri
63102 Y -- FACILITIES LINE SECTION 1 -- 5TH & MISSOURI TO WASHINGTON PARK
SOL SB2323 DUE 040298 POC Deborah Rowey, Contract Specialist E-MAIL:
Deborah Rowey, drowey@bsda.org. INVITATION FOR BIDS FOR FACILITIES LINE
SECTION 1 5th & MISSOURI TO WASHINGTON PARK FOR THE ST. CLAIR COUNTY
METROLINK EXTENTION SEALED BID NO. ML-97-SB-2323 The Bi-State
Development Agency (Agency) is soliciting bids for the construction of
Facilities Line Section 1 -- 5TH & Missouri to Washington Park. The
Disadvantage Business Enterprise (DBE) participation goal is 25%. DBE
firms are invited to propose directly or with another firm. The
facilities mainline work consists of all construction associated with
the preparation of the mainline trackbed, up to and including the
subballast. The mainline work is comprised of the following: Demolition
and site clearing (excluding building demo), earthwork (excavation,
embankments, hauling), construction of mainline structures (bridges,
major drainage culverts, retaining walls, and catenary pole
foundations), construction of roadways including future proposed
at-grade crossings, relocation of existing utilities (storm sewer,
sanitary sewers, water lines), construction of new utilities (conduits,
duct banks), construction of subballast cap, and construction of
erosion control (seeding, sodding, select ground cover). The facilities
work for the passenger stations/park-and-ride lots consists of all
construction for the preparation of the passenger station platforms and
the park-and-ride lots excluding most station finishes work. The
passenger stations/park-and-ride lots work is comprised of the
following: Demolition and site clearing (excluding building demo),
earthwork (excavation, rough grading, finish grading), construction of
structures (station platforms, communication buildings, canopy
foundations, light pole foundations), construction of asphalt roadways
and parking lots, construction of concrete roadways including concrete
curb and gutter, construction of concrete flatwork (sidewalk, plaza
paving, stairs, handicap ramps), relocation of existing utilities
(storm sewers, sanitary sewers, water lines), construction of new
utilities (water lines, storm sewers, sanitary sewers, conduits,
irrigation), and construction of erosion control (seeding, sodding,
select ground cover). Pre-Bid Conference: 2/18/98 Bid Opening: 4/2/98
Questions should be addressed to Rebecca Howe, Director, MetroLink
Contracts & Procurement. Fax questions to (314) 923-3022 or mail to
Bi-State Development Agency, 707 N. 1st St., St. Louis MO 63102. Please
include the sealed bid number, your company name, and complete address
and both telephone and fax numbers. Copies of the Project Manuals and
Drawings may be obtained by appointment only beginning February 2,
1998, Monday -- Friday between the hours of 8 a.m. -- 12 p.m. and 1
p.m. -- 5 p.m. at the MetroLink Document Control Department by calling
Ms. Sandra Armstrong (314) 982-1400 Ext. 1329. The cost for a set of
plans and contract documents is $525.00. This cost is non-refundable.
Each request must be accompanied by either a certified check, money
order, or cashiers check payable to Bi-State Development Agency.
Written requests including arrangements for pick up for plans and
documents should be addressed to Ms. Sandra Armstrong, MetroLink,
Second Floor, 707 N. First Street, St. Louis, Missouri 63102. Shipping
costs are the responsibility of the requestor. Therefore, all
requestors desiring to have a set(s) of plans and documents mailed are
required to provide Ms. Sandra Armstrong with a Federal Express, UPS
etc. account number. Mailed-in requests will be returned, if this
information is not provided. (0014) Loren Data Corp. http://www.ld.com (SYN# 0089 19980120\Y-0004.SOL)
Y - Construction of Structures and Facilities Index Page
|
|