COMMERCE BUSINESS DAILY ISSUE OF FEBRUARY 5,1998 PSA#2026U. S. Army Corps of Engineers, Omaha District, 215 North 17th Street,
Omaha, NE 68102-4978 Y -- FOGGY BOTTOMS EROSION REPAIR, OAHE DAM, SOUTH DAKOTA SOL
DACW45-98-B-0023 DUE 032498 POC Contract Specialist: Lee McCormick,
402/221-4045 WEB: Omaha District Contracting Division Homepage,
http://ebs.mro.usace.army.mil/EBS/CONTRACT.HTM. E-MAIL: Lee McCormick,
Lee.M.McCormick@usace.army.mil. On or about 18 February 1998, this
office will issue Invitation for Bids for the construction of FOGGY
BOTTOMS EROSION REPAIR. Bids will be opened on or about 24 March 1998.
This solicitation is unrestricted and open to both large and small
business participation. Contractors interested in inspecting the site
of the proposed work should contact the Project Manager's Office, Oahe
Project, U.S. Army Corps of Engineers, P.O. Box 997, Pierre, South
Dakota 57501, Telephone (605) 224-5862 ext. 3204. FAX (605) 224-5945.
The work will include the following: (Approx. quantities) 16,000 tons
of Riprap; 16,000 cubic yards of compacted fill; and 10,000 square
yards of geotextile fabric. The estimated construction cost of this
project is between $500,000 and $1,000,000. Contractor's Quality
Control will be a requirement in this contract. Large business concerns
submitting bids for services exceeding $500,000 or for construction
exceeding $1,000,000, shall comply with Federal Acquisition Regulation
52.219-9 regarding the requirement for a subcontracting plan. The U.S.
Army Corps of Engineers considers the following goals reasonable and
achievable for fiscal year 1998: (a) Small Business: 61.2% of planned
subcontracting dollars. (b) Small Disadvantaged Business: 9.1% of
planned subcontracting dollars. (c) Women Owned Small Business: 4.5% of
planned subcontracting dollars. The Contractor will be required to
commence work within 10 days after notice to proceed and complete the
work 120 calendar days after receipt of Notice to Proceed. Provisions
will be included for liquidated damages in case of failure to complete
the work in the time allowed. Performance and payment bonds will be
required. Plans and Specifications will be provided free of charge. All
requests for solicitation packages should be made on the Omaha District
website or in writing and no later than 14 days prior to bid opening.
After such time, packages will be furnished if supply is available. It
has been determined that the number of sets be limited to one (1) per
firm. Ordering of plans and specifications shall be by written request
or register on the Omaha District website:
http://ebs.mro.usace.army.mil/EBS/Contract.htm or faxed to (402)
221-4530 with the following information: 1) Solicitation Number and
Project Name; 2) Name of Firm; 3) Point of Contact; 4) Mailing Address;
5) Street Address for Parcel Delivery Service; 6) Telephone and Fax
Phone Numbers with Area Code (FAX numbers are mandatory to ensure the
receipt of any amendments that may be faxed); 7) Level of Participation
(General Contractor, Subcontractor, Supplier or Plan Room); and 8)
Large Business, Small Business, or Small Disadvantaged Business. If any
of the information changes during the advertisement period, submit the
information via e-mail to lee.m.mccormick@usace.army.mil or by written
request or fax. Failure to provide the above information and any
changes may cause a delay in receiving plans, specifications and
amendments. Questions regarding the ordering of same should be made to
the Contract Specialists: Lee McCormick at telephone number
402-221-4045 or Dawn Thompson at telephone number 402-221-4811.
Telephone calls regarding Small Business matters should be made to:
402-221-4110. Telephone calls on contents of drawings and
specifications should be made to Specification Section at: (402)
221-4547. (0034) Loren Data Corp. http://www.ld.com (SYN# 0135 19980205\Y-0012.SOL)
Y - Construction of Structures and Facilities Index Page
|
|