COMMERCE BUSINESS DAILY ISSUE OF MARCH 27,1998 PSA#2061Idaho Panhandle National Forests, 3815 Schreiber Way, Coeur D'Alene,
Idaho 83815-8363 Y -- LOOP CREEK BRIDGE REPLACEMENT SOL RFQ R1-04-98-43 DUE 052798 POC
Contract Clerk, (208) 765-7497 Project involves construction of a
single lane 50 ft. span concrete bridge. The work consists of
cast-in-place structural concrete footings and columns, precast
concrete cap and wingwalls and a prestressed tri-deck superstructure
with curbs. Other work items include; removal of the existing timber
bridge, structural excavation, machine-placed riprap, temporary bypass
construction, approach roadway construction and associated minor work
items. St Joe Ranger District, Shoshone County, Idaho. Estimated start
work June 17, 1998 and complete by September 30, 1999. Price range
between $25,000 and $100,000. See Note 26. (0083) Loren Data Corp. http://www.ld.com (SYN# 0133 19980327\Y-0002.SOL)
Y - Construction of Structures and Facilities Index Page
|
|