COMMERCE BUSINESS DAILY ISSUE OF MARCH 31,1998 PSA#2063JACKSONVILLE DISTRICT OFFICE, U.S. ARMY CORPS OF ENGINEERS, P.O. BOX
4970, JACKSONVILLE, FL 32232-0019 Z -- MAINTENANCE DREDGING, 38-FOOT PROJECT, CUT-3 THROUGH CUT-6, CUT-7
THROUGH CUT-13, AND CUT-39 THROUGH CUT-42, JACKSONVILLE HARBOR,
JACKSONVILLE, FLORIDA SOL DACW17-98-B-0010 DUE 051298 POC Contract
Specialist Vicki Tipton (904) 232-1146 (Site Code DACW17) The project
consists of dredging approximately 493,000 cubic yards of material from
Cut-3 through Cut-6 for the Base Bid. In addition to the Base Bid, Base
Bid Option A will add approximately 133,000 cubic yards of material
from Cut-7 through Cut-13 and Bid Option B will add approximately
186,000 cubic yards of material from Cut-39 through Cut-42. The dredged
material from the Base Bid and Bid Option A shall be placed in the
Beach Disposal Area south of the south jetty. The material from Option
B shall be placed in Disposal Area 2A-Buck Island. The required depth
for all areas, Base Bid, Bid Option A, and Bid Option B is 40 feet
plus 1 foot allowable overdepth. Disposal Area 2A-Buck Island is
located at a maximum of approximately 30,300 feet from the areas to be
dredged and the Beach Disposal Area is located a maximum of
approximately 27,000 feet from the areas to be dredged. Work also
includes Turbidity and Endangered Species Monitoring, and Beach
Tilling. Magnitude of construction is between $5,000,000 to
$10,000,000. Pre-Solicitation Notice will be issued on or about 20 Mar
98. Invitation DACW17-98-B-0010 will be issued on or about 09 Apr 98
and opened on or about 12 May 98. Cost of Plans and Specifications is
$40.00. Checks should be made payable to FAO USAED Jacksonville, and
sent to U.S. Army Corps of Engineers, Jacksonville, Florida. THIS IS AN
UNRESTRICTED ACQUISITION. NOTE: Contracting information for the
Jacksonville District is now available at our (0086) Loren Data Corp. http://www.ld.com (SYN# 0146 19980331\Z-0020.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|