COMMERCE BUSINESS DAILY ISSUE OF APRIL 15,1998 PSA#2074Operational Contracting Office, 8110 Industrial Dr., Suite 200, USAF
Academy, CO 80840-2315 C -- OPEN-END IDIQ A-E CONTRACT FOR ARCHITECTURAL SERVICES AT THE USAF
ACADEMY, CO SOL F0561198R0258 DUE 051298 POC Contact John Peters,
Contracting Officer, (719) 333-2735 A-E Open End Title I, Title II and
other Architect-Engineer (A-E) Services at the United States Air Force
Academy CO, for a broad variety of maintenance, repair, and new
construction projects. The performance period will be one year from
date of award plus four (4) one-year option periods that will be
unilaterally exercised at the government's discretion. Services
required may be field investigations, recommendations, studies,
reports, analysis, cost estimates, specifications, product research,
record documents research, preparation of construction drawings, and
presentations to coordinating agencies. Designs may require asbestos
and lead based paint removal. This contract may also include planning,
GIS, maintenance, repair and construction of all Academy facilities.
Title II delivery orders may involve direct consultation with
construction contractors. Construction management services, as-built
services and peer review services may be required. Submittals should
include proposed subconsultants for architectural, environmental
(including asbestos and lead paint), roofing, and each of the major
engineering disciplines required for a complete design. This open-end
contract may include asbestos & lead paint, roofing, and each of the
major engineering disciplines. This open-end contract may include the
design of new systems, repair and replacement of existing systems,
utilities, substations, electrical distribution, heat plants, and DDC
control systems. One architectural firm will be selected for project
number 99-0105. Architect-Engineer firms that meet the requirements
described in the announcement are invited to submit the following in an
original and one copy; (A) Standard Form 254, Architect-Engineer and
related services questionnaire; (B) Standard Form 255,
Architect-Engineer related services for specific projects. To be
included with the Standard Form 254 and 255 shall be a cover letter
specifically addressing each of the below listed criteria in sequence.
Criteria 1 and 2 below are equally of the greatest importance, with
the remainder of the criteria of lesser importance, but approximately
equal to each other. Criteria forming the basis for selection by two
formal selection boards will include, but will not be limited to: (1)
Specialized Experience: Expertise of the firm in facilities and large
scale academic complexes; Technical competence in renovation and
upgrade in the type of work required, including, where appropriate,
experience in energy, conservation, pollution, prevention, waste
reduction, and use of recovered material; (2) Professional
qualifications of experienced key personnel and consultants. Principles
and Project Managers of A-E firms must hold a professional degree and
a registered architect, licensed in the State of Colorado. Project
Managers of sub-consultants must hold a professional degree and be a
registered professional engineer, licensed in the State of Colorado;
(3) Capacity of firm to handle several different requirements in
different required time limits; (4) Past performance on contracts both
Government and Private in terms of cost control, quality of work, and
compliance with performance schedules; (5)Volume of work: Prior DOD
Awards, specifically list all DOD contracts awards the firm completed
for the previous twelve months to include fees; (6) Previous work at
the United States Air Force Academy; (7) CADD capabilities; (8)
Location in general geographical area of the Air Force Academy; (9)
Identification and commitment to small business and to small
disadvantaged business, historically black college and university, or
minority institution performance of the contract, whether as a joint
venture, teaming arrangement, or subcontractor. Failure to supply data
in the cover letter for criteria 1 through 9 above may result in
disqualification of the firm. Based on these criteria, the USAFA
Preselection Board will reduce the field of submitting A-E firms to a
maximum of six (6). The qualifications of these six firms will be
reviewed by the USAFA Final Selection Board, which will independently
rank the six firms. Evaluations of the three top-rated firms will
include interviews by the Final Selection Board members. The firm
receiving the highest ranking from the Final Selection Board will be
the first choice for selection, with the second and third ranked firms
serving as alternates. The firm ranked most qualified will be sent a
Request for Proposal (RFP) with the intent to negotiate rates. It is
anticipated that the clause "Small, Small Disadvantaged and Women-Owned
small Business Subcontracting Plan" (FAR 52.219-9) will be included in
any resulting Request for Proposal. Offerors should review the
applicability of the clause and consider the requirements of this
clause when assembling their team of subconsultants, providing, if
required sufficient representation to achieve established goals. The
firm awarded a contract is guaranteed a minimum of $5,000.00 in fees
for A-E Services. As projects are identified, delivery orders will be
issued. No single delivery order, including subsequent modifications
may exceed $299,000.00 in fees. Fees may not exceed $750,000.00 in any
contract year. This includes modifications to delivery orders issued
in that year. An exception to this limitation is the initial delivery
order to start the contract. This order may exceed $299,000.00, but can
not exceed the maximum limitation of the contract of $750,000.00 for
each year. Appropriate data in response to this notice must be received
by 12 May 98. This requirement is being advertised unrestricted in
accordance with the Small Business Competitive Demonstration Program.
This announcement is not a request for proposals. (0100) Loren Data Corp. http://www.ld.com (SYN# 0018 19980415\C-0002.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|