6100, MSC 7902, Bethesda, MD 20892 66 -- INSTRUMENTS AND LABORATORY EQUIPMENT SOL NHLBI-PS-98-280 DUE
051598 POC Cecilia D. Morales, Purchasing Agent (301)435-0369, Debra C.
Hawkins, Chief, Procurement Section, (301) 435-0366 This is a combined
synopsis/solicitation for commercial items, prepared in accordance
with the format in FAR subpart 12.6 as supplemented with additional
information included in this notice. This announcement constitutes the
only solicitation; proposals are being requested and a written
solicitation will not be issued. The solicitation number
NHLBI-PS-98-280 and is issued as Request For Quotation (RFQ). The
solicitation includes all applicable provisions and clauses in effect
through the Federal Acquisition Circular 97-03. This is a small
business set aside. The Standard Industrial Classification (SIC) code
is 3821, size standard 500 employees. This acquisition intends to
purchase a Controls Retrofit a component of a Fermentor, Model 500L,
Government owned equipment, manufactured by ABEC, Inc. of Philadelphia,
PA 19178. The specifications of the Controlled Retrofit is as follows:
and installation. One (1) each Elephant Ear and installation. One (1)
charge for removing the cooling coil, and one (1) eachSteamlock
Assembly and installation. This equipment is designed to restore a
300-liter fermentor manufactured by ABEC, Inc. (1) INSTRUMENT
ENCLOSURE: to be installed in a new Nema-12 electrical cabinet and
Panel mount instruments will be mounted in the door of the enclosure;
(2) AGITATION: Display -- digital readout on A-B PLC, Control --
A-B-PLC control of output for RPM control; (3) TEMPERATURE: Sensor --
Pyromation RTD, Amplifier -- Burns, 4-20 mA isolated output, Display --
Digital readout on A-B-PLC, Accuracy -- (+/-) 0.2 degree C., Control --
A-B-PLC control of existing heat, cool, and steam valves in conjunction
with recirculating pump semi-auto sterilization cycle after manual
setup with vessel empty; pH: Sensor -- Ingold, gel filled, pressurized
electrode with holder, Amplifier -- Ingold model 2301 with temperature
compensation, 4-20 mA, Display -- Digital readout on Amplifier DPM and
A-B PLC, Control -- A-B-PLC control of existing automatic solenoid
valves; (4) AIR AND GAS FLOW: Sensor/Amplifier -- Two (2) Brook: Mass
Flow Controllers for Air and O/2 to sparge 4-20 mA input/output,
Display -- Digital readout on A-B PLC, Control -- A-B PLC control of
O/2 and Air flows; (5) DISSOLVED OXYGEN: Sensor -- Ingold,
polarographic, in place sterilizable electrode, Amplifier -- Ingold
model 4300, 4-20mA output, Display -- digital readout on Amplifier DPM
and A-B PLC, Control -- A-B PLC control of O/2 flow, agitation, air
flow and back pressure; (6) PRESSURE: Sensor -- Rosemount sanitary
diaphragm type transducer type 2088 transmitter 4-20 mA, Display --
Digital readout on A-B PLC, Control Existing vessel back pressure
regulator; (7) LEVEL(FOAM): Sensor/Transmitter -- Luminite level probe
and transmitter 4-20 mA, Control -- A-B PLC Control of existing
automatic solenoid valve; (8) ADDITIONAL DISPLAYS: Sensor -- Existing
addition tank level probes, Display -- Acid tank level, Base tank
Level, Antifoam tank level and Nutrient tank level. (9) PLCAND OIT
SOFTWARE: Programmable Logic Controller (PLC); Hardware -- PLC will be
for sequential and loop control of processes, Power Requirements --
Controller shall be supplied for use on 120 VAC with an isolated
ground, Battery backup -- Lithium battery/backup of memory will be
required, CPU Capacity -- CPU shall be required with 25% of memory
capacity for future expansion after all programming is complete;
Software -- PLC Programming, Structure -- The rungs of logic must be
written in process variable categorized form which will be determined
by the processes controlled, Internal Documentation -- The program
ladder logic must be fully documented; (10) OPERATOR INTERFACE TERMINAL
(OIT): Hardware -- Local operator interface shall be with keypad entry,
Software -- Screen Menus -- A hierarchical screen menu system shall be
provided. The top level must be an overview screen to display process
variables, set points, and loop status (auto manual, cascaded, or
off). Three tiers of menus, each protected with a password shall be
selected from the overview screen. The tiers diagram must be submitted;
Security -- From the overview screen, selection must be made to enter
the operator, maintenance, or engineer screens. Upon selection of
screen area desired, the user shall be prompted for a password to enter
all areas, Operator Access -- Full access to loop controls, dissolved
Oxygen cascade control hierarchy and SIP setup, Engineering Access --
Full access to DO cascade setting such as high and low limits for
cascade switch points and tuning constants; (11) DOCUMENTATION: Two (2)
copies of approval drawings on pressure vessels must be submitted prior
to commencement of manufacturing. This includes assembly type shop
drawings from the vessel fabricator, Technical cut sheets for
components related to instrumentation and control,
Operation/instruction manuals, installation/maintenance manuals,
calibration data for factory calibrated components, wiring schematics
for instrumentation and control components, recommended spare parts
list, approval drawings and list of materials which shall include
assembly drawings and electrical schematics, as-built drawings and list
of materials, disk copy of controller source code program, disk copy of
as-built drawings on Auto-Cad version 12, must be available on request.
The instruments must calibrated and tested, and must be warranted
against manufactures defects. The Government's desired final delivery
and acceptance schedule is December 31, 1998 at 9000 Rockville Pike,
Bethesda MD. 20892. The provisions of FAR Clause 52.212-1, Instructions
to Offerors -Commercial Items, applies to this acquisition. The
provisions of FAR Clause 52.212-2, Evaluation -- Commercial Items is
applicable to this acquisition. Award will be made on the technical
merits of the instrument proposed meeting the Government's
specifications. Price will be a secondary factor for award. The Offeror
must include a completed copy of the provision of FAR Clause 52.212-3,
Offeror Representations and Certifications -- Commercial Items with
its offer. The provisions of FAR Clause 52.212-4, Contract Terms and
Conditions -- Commercial Items, applies to this acquisition. The
offeror must provide two (2) copies of the proposal and descriptive
literature inclusive of all specifications and workmanship as part of
the quotation. FAR Clause 52.212-5, contract Terms and Conditions
Required to Implement Statutes of Executive Orders -- Commercial Items
-- Deviation For Simplified Acquisitions, applies to this acquisition.
Interested vendors capable of furnishing the government with the
equipment specified in this synopsis should submit two (2) copies of
the quotation to the below address. The quotation must reference
"Request for Quotation" Number NHLBI-PS-98-280. Quotations will be due
fifteen (15) calendar days from the publication date of this synopsis
by 3:00 p.m., E.T. All responsible sources may submit a quotation,
which if timely received, shall be considered by the agency. Quotations
must be submitted in writing to the National Heart, Lung, and Blood
Institute, Contracts Operation Branch, Procurement Section, Rockledge
Building 2, Room 6143, 6701 Rockledge Drive, Bethesda, MD 20817-7902,
Attention: Ms. Cecilia D. Morales, Purchasing Agent, Fax Number (301)
480-3345. Fax quotations will only be accepted if dated and signed by
an authorized representative. (0118) Loren Data Corp. http://www.ld.com (SYN# 0284 19980430\66-0018.SOL)