COMMERCE BUSINESS DAILY ISSUE OF MAY 13,1998 PSA#2094Naval Research Laboratory, Attn: Code 3230, 4555 Overlook Avenue, SW,
Washington, DC 20375-5326 66 -- INSTRUMENTS AND LABORATORY EQUIPMENT SOL N00173-98-R-MP02 POC
Susan Kelly, Contract Specialist, Code 3230.SK (202) 767-6815,
Contrating Officer, Carol Parnell, Code 3230.CP, (202) 767-6815 WEB:
http://heron.nrl.navy.mil/contracts/home.htm,
http://heron.nrl.navy.mil/contracts/home.htm. This notice is an
amendment to provide questions and answers for the
synopsis/solicitation published in the CBD on 20 Apr 98. 1. Q) Does the
Contractor provide installation at the three individual locations (plus
option) mentioned? A) Contractor provides installation at all of the
sites. They also will align the antennas on the satellite. 2. Q) Does
the Contractor ship the antennas to NRL, Wash. DC or to the three
individual locations? A) Antennas are to be shipped to the sites at
time of installation. 3. Q) Can my quote be faxed to you, or must it be
sent via mail? A) As per the solicitation, 2 copies of the PROPOSAL
must be delivered to NRL. Facsimile transmission has NOT been
authorized. 4. Q) What will be the max required bandwidth of the
circuits to be supported? A) IF frequency range for transmit and
receive: 70 MHz +/- 27 MHz minimum tuning in 1 MHz steps. Bandwidth =
70 MHz min. 5. Q) Is the following statement correct? NRL requires the
first three antenna systems (CLIN 0001) to be installed bythe contract
awardee at the sites specified and the forth antenna system (CLIN 0002)
be delivered to NRL, Wash DC, but not installed. A) All antennas are to
be installed by awardee. 6. Q) Ten watts at C-Band is very low power
requirement. Will it support the required bandwidth? A) Yes. 7. Q) Do
we supply the antenna mounts? If so, in an AZ/EL mount the requirement?
A) Yes. 8. Q) What is the exact frequency range to be covered in MHz?
A) Uplink: 5.85 GHz -- 6.65 GHz, Downlink: 3.4 GHz -- 4.2 GHz. 9. Q)
Will your base in Antigua accept and clear customs at the St. John's
Dock. This must be done by the end user. Will the Base provide
transportation from dock to the base? A) The program sponsor will
handle shipping of equipment to Antigua and Ascension Island. 10. You
state that delivery must be made in 30 days to the individual sites.
The installer of the antennas cannot install all three simultaneously.
Each site needs 4-5 days installation plus travel time to the next
site. We request the installation be staggered at 10-day intervals for
each base. A) ROCC and JDMTA will be installed simultaneously. Other
site installations will be staggered. There will be about a month
separation between installations. 11. Q) We request that we receive
confirmation from you that each site is prepared before we ship the
antennas and send installer. A) The sponsor won't allow installation
until the sites have been prepared. NRL will coordinate the dates with
the Contractor. NO FURTHER QUESTIONS WILL BE ADDRESSED. The closing
date is extended to 018 May 98. All other terms and conditions remain
the same. Offers must be delivered to Contracting Officer, Code
3230.SK, Bldg. 222, Rm 115A, Naval Research Laboratory, 4555 Overlook
Ave., SW, Washington, DC 20375-5326 and received no later than 4:00
P.M. EST on 18 May 1998. The package should be marked RFP
N00173-98-R-MP02, Closing Date: 18 May 1998. For information regarding
this solicitation contact Susan Kelly, Contract Specialist at (202)
767-6815. All responsible sources may submit a proposal, which shall be
considered by the agency.**** (0131) Loren Data Corp. http://www.ld.com (SYN# 0278 19980513\66-0010.SOL)