COMMERCE BUSINESS DAILY ISSUE OF MAY 13,1998 PSA#2094Department of Transportation, Federal Aviation Admin. (FAA),
Procurement Branch, AWP-55, P.O. Box 92007, WWPC., Los Angeles, CA
90009-2007 C -- A & E DESIGN SERVICE FOR NEW AIR TRAFFIC CONTROL TOWER, GRAND
CANYON NATIONAL PARK AIRPORT, GRAND CANYON, AZ SOL DTFA08-98-R-03217
POC Michelle Turner, Contracting Officer or James Travers, Contractor
Rep. (310) 725-7546 WEB: Chick Here to Download a copy of Synopsis,
http://www.awp.faa.gov/organ/logist.htm. E-MAIL: Click Here to Contact
Contractor Rep. via e-mail, james.travers@faa.dot.gov. 1. CONTRACT
INFORMATION: Architectural and Engineering services are required for
environmental assessment, surveying, site investigation, engineering
studies, project definition phase, preliminary and final design, and
construction phase services (option) for the subject project. This
announcement is open to all firms regarless of size. A firm-fixed price
contract will be negotiated. The contract is anticipated to be awarded
in August 98 and complete by October 99. PROJECT INFORMATION:
Approximately 95-ft tall tower with a 525-sq. ft. Cab and adjoining
3000 sq. ft. Base Building. The tower will include a breakroom, toilet
facilities, as well as mechanical and electronic support equipment
within the floors below the cab. The Base Building will house the
administrative support facilities, mechanical and electronic equipment
and emergency backup power equipment. The project shall include
support for the transition of related FAA facility equipment control to
the new tower. The estimated construction cost is $5,000,000 to
$10,000,000. SELECTION CRITERIA: The selection criteria are listed
below in descending order of importance (first by major criterion and
then by each sub-criterion). Criteria a-e are primary. Criteria f-g are
secondary and will only be used as "tie-breakers" among technically
equal firms. a. Specialized experience and technical competence in: (1)
Structural design of high-rise facilities per the 1997 Uniform Building
Code (UBC), particularly the Grand Canyon, AZ area. (2) Design of FAA
Airport Traffic Control Towers. (3) Design of fire protection systems
(4) HVAC designs for high rise facilities. (5) Power studies and short
circuit analysis for critical facilities. (6) Stormwater management
and erosion control. (7) Computer aided design and drafting, including
3-dimensional analysis. (8) Computer aided cost estimating. (9)
Computer aided project managment. (10) Producing quality designs based
on evaluation of a firm's design quality management plan. b.
California energy standards (Title 24), County of Coconino Plan Check
procedures and permit requirements, Arizona Department of
Transportation procedures and permit requirements, United States Forest
Service procedures and permit requirements, Federal Aviation
Administration regulations including FAA Orders pertaining to
construction. (0128) Loren Data Corp. http://www.ld.com (SYN# 0016 19980513\C-0003.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|