COMMERCE BUSINESS DAILY ISSUE OF JUNE 1,1998 PSA#2106Public Works-Engineering, 19th Floor, City Hall, 414 E 12th Street,
Kansas City, MO 64106 Y -- NEID CHESNUT OUTFALL, 2.4 METER PIPE, TUNNEL, AND LEVEE WORK SOL
KCMO Project No. 3506 DUE 063098 POC Jim Wattenbarger, 816-274-2080,
for scope inquiry Sheila McDaniel, 816-274-1587, for bid documents
E-MAIL: click here, Jim_Wattenbarger@KCMO.org. The work will consist of
installation of 229 Meters of 2.4 M concrete pipe, of which 57 Meters
is tunnel under railway, plus a temporary levee and detour road, plus
Missouri River levee reconstruction, 3 large structures, and
appurtenances. Economic Development Administration is partially funding
this project. (0148) Loren Data Corp. http://www.ld.com (SYN# 0135 19980601\Y-0001.SOL)
Y - Construction of Structures and Facilities Index Page
|
|