COMMERCE BUSINESS DAILY ISSUE OF JUNE 29,1998 PSA#212628th Contracting Squadron, 2704 George Drive, Suite 1, Ellsworth AFB,
SD 57706-4910 Z -- DISCONNECT AND CAP LINES SOL F39601-98-B0006 DUE 081498 POC Mitch
Williams 605-385-1746 WEB: F39601-98-B0006 DISCONNECT AND CAP WATER
LINES, http://www.ellsworth.af.mil/~lgck/const/8b0006/8b0006.html.
E-MAIL: SrA Mitch Williams OR Dave Pakalski,
williamm@cons28.ellsworth.af.mil OR pakalskd@cons28.ellsworth.af.mil.
Furnish all labor and materials to disconnect and cap the 4" and 6"
service distribution main from the 16" main and repair it. More
specifically, will excavate both sites prior to capping West Nike and
South Nike service distribution line and 16" main. Excavation locations
to be identified by CE personal. The 4" and 6" service distribution
lines will be disconnected from the 16" main and capped. The 16" main
at both locations will then be repaired with manufactures's recommended
saddles. A joint inspection and reactivation of 16" line and inspection
of service line capping will be conducted by 28 CES Line Maint. and
Sewage Treatment and Project Engineer with the contractor prior to
backfill. Backfill will not commence until approved by 28 CES. Backfill
will be industry standard. The 16" main operational capability and
excavation area will be restored to original condition to concrete
encasement. The 16" main will be isolated by 28 CES Line Maintenance.
The isolation and nonoperational capability of the16" main will only be
for 6 hours downtime at each site. Posted 06/25/98 (0176) Loren Data Corp. http://www.ld.com (SYN# 0161 19980629\Z-0046.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|