COMMERCE BUSINESS DAILY ISSUE OF JUNE 30,1998 PSA#2127USDI, Bureau of Land Management, Oregon State Office (952), P. O. Box
2965, Portland, Oregon 97208-2965 Z -- NESTUCCA ACCESS ROAD PAVING & BRIDGE REPLACEMENTS SOL
1422H952-B98-3050 DUE 081498 POC Tom Fulton, 503-952-6218 E-MAIL: BLM,
or952mb@or.blm.gov. Work consists of constructing two precast
prestressed concrete bridges, one across the Nestucca River at Station
873 and the other across Elk Creek; and improving portions of the
Nestucca Access Road. Work includes demolition and disposal of existing
bridges and drainage culverts; construction of concrete
superstructures, substructures, and retaining walls; gabion walls,
culvert replacement; placing riprap; asphalt patching and paving; chip
sealing; installing guardrail. Project site is located in Tillamook
County, Salem District, Oregon. Project range is between $1,000,000 and
$5,000,000. Estimated start work is September 1, 1998. Bonds are
required -- Bid Bond: 20%; Performance Bond: 100%; and Payment Bond:
40%. All responsible sources may submit an offer which will be
considered. Posted 06/26/98 (0177) Loren Data Corp. http://www.ld.com (SYN# 0158 19980630\Z-0037.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|